Installation instructions geoTHERM VWS/VWW 0020057444_01
14
300 mm
10 mm
600 mm
300 mm
300 mm
Fig. 4.2 Minimum clearances for installing the heat pump
4.4
Assembly/Installation at a glance
– Remove packing material.
– Remove transportation safety devices.
– Transport the heat pump to the installation area.
– Position and align the heat pump in the intended as-
sembly location.
– Remove the upper cladding.
– Remove the front cladding.
– Connect the on-site piping.
– Carry out the electrical installation.
– Fill the heating circuit.
– Fill the heat source circuit.
– Fit the cladding.
– Fit the operating console.
– Carry out the initial commissioning.
– Fill out the start-up checklist.
– Hand over system to the user and familiarise him with
it.
4.5
Preparatory work in the installation area
1
1
2
3
3
Fig. 4.3 Preparatory work in the installation area
• Make sure that the substrate is sufficiently stable (see
Chap. 4.2 "Requirements for the installation site").
• Make at least two bore holes, bearing in mind the di-
mensions of the unit and its connections (
1
).
• Each pipe from the heat source requires its own bore
hole.
• Special pipe feedthroughs must be used if there is a
risk of ground water penetration (follow the manufac-
turer's instructions).
• Take account of the distances to the core barrels for
the rest of the installation.
• Pass the heat source pipes (
2
) from the outside into
the installation area.
• Lay the heat source pipes (
2
) centrally in the bore
holes (
1
) to facilitate all-round thermal insulation.
• Seal the annular gap (
1
) as shown with foam insulation
(e.g. PE foam) (
3
).
• Insulate the heat source pipes in cellar areas against
vapour diffusion, as condensation will otherwise accu-
mulate (pipe temperature can be as low as - 15 °C).
4 Assembly and installation
Summary of Contents for geoTHERM VWS Series
Page 1: ...For the heating engineer Installation instructions geoTHERM Heat pump VWS VWW GB ...
Page 90: ......
Page 91: ......
Page 92: ...0020057444_01 GB 072008 ...