10
Figure 9: Jacket Assembly
Figure 7: Canopy Gasket Installation
Figure 8: Canopy Installation
D.
Install Canopy.
1. Install ½" thick x 1" wide ceramic fiber gasket. See
Figure 7.
2. Position canopy on ceramic fiber gasket. See Figure
8.
3. Attach canopy using ¼" carriage bolts, nuts, and
washers provided.
E.
Inspect joints between sections.
They were factory
sealed. If there are any openings due to shipment or
handling, reseal with boiler putty.
F.
Install Jacket.
See Figure 9.
1. Models IN7I-IN12: remove 3 inch diameter
knockouts in jacket top panels.
2. Raise rear panel under rear flange of canopy and rest
on floor. Position rear panel and secure to jacket side
panels with sheet metal screws. For Models IN10-
IN12, secure jacket upper rear panels to side panels
with sheet metal screws.
3. Secure both jacket side panels to base with sheet
metal screws.
4. Position front tie bar and secure to jacket side panels
with sheet metal screws.
5. Position vestibule panel and secure to side panels
with sheet metal screws.
6. Attach Rating Label and Vent Damper Instruction
Label at designated locations on vestibule panel.
7. Install top panels by placing over and around outside
of side and rear panels. Seat fully and secure with
sheet metal screws.
II. Knocked-Down Boiler Assembly (continued)
Summary of Contents for INDEPENDENCE
Page 4: ...4 Figure 1 Dimensional Drawing...
Page 56: ...56 Manifold and 1 Main Burners XI Repair Parts continued...
Page 62: ...62 XI Repair Parts continued...
Page 64: ...64 XI Repair Parts continued...
Page 72: ...72 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net...