STEP 7
SET ACTUAL DATE
• Press remote "Actual Date" (Calendar symbol) button.
Year will appear and first segment will flash.
• Press remote's numbered buttons to enter desired
year. As each number is entered, the next segment
will flash. After entering year, press
ENTER
button.
Actual month and day-date will appear with bottom
colon dot, and first segment number will flash.
• Press remote's numbered buttons to enter desired
month and date. As each number is entered, the
next segment will flash. After entering the month and
date, on the remote, press
ENTER
button.
EXAMPLE:
November 14, 2017 date. Press
ACTUAL DATE
button. Enter numbers 2-0-1-7, press
ENTER
button, enter
numbers 1-1-1-4, press
ENTER
button.
STEP 8
DISPLAY FORMATS
TO DISPLAY:
• NUMBER OF COUNT DAYS ONLY – Press
DAYS
button.
This displays only the count days.
• DATE ONLY – Press
DATE
button. This displays only the
month day.
• CLOCK ONLY – Press
CLOCK
button. This displays
only the actual time.
• ALL – Press
ALL
button. This displays number of
count days, date (month.day), and actual time in
sequence each for 10 seconds.
STEP 9
COUNTING OPEN WORK WEEK DAYS
To only count actual work days when workplace is open,
i.e. open 5 days and closed 2 days.
Determine the date for FIRST open work day after closed
days – example: If only counting work days Monday
through Friday (and not counting Saturday and Sunday)
the date for Monday would be the FIRST work date.
The FIRST work date must be current or future date. If
using future date, OFF days will continue to calculate
until that date occurs. It is best to set the work week
days on the actual FIRST work date to avoid counting
issues.
• Press remote
WORK DAYS
button. Year will appear
and first segment will flash.
• Press remote's numbered button to enter desired
year. As each number is entered, the next segment
will flash. After entering year, press
ENTER
button.
Month and day-date will appear with the bottom
colon dot, and first segment number will flash.
• This is to enter the FIRST date of the work week days.
Press remote's numbered buttons to enter desired
month and date. As each number is entered, the
next segment will flash. After entering the month and
date, press
ENTER
button. Single digit will appear.
• This is the number of work days for the display to
count. Press remote's numbered button, choice of
1 through 7. Afterwards the number will flash. Press
ENTER
button. This sets the specific number of work
days to count per week.
EXAMPLE:
November 18, 2017 is the
first day of the 5-day work week (only
counting the working days). Press
WORK DAYS
button. Enter number
1-1-1-8, press
ENTER
button, enter
number 5, press
ENTER
button.
NOTE: Safe days counter doesn't account for
holidays or adjust time for daylight savings
time. Please update the display when the
holiday or time change occurs.
OPERATION CONTINUED
Days Open
Count Days Only
Date Only
Clock Only