Step 5:  

 

If you have removed all the segment 

before you go any further, you need to 

check to make sure the segments are 

aligned correctly. 

 

It is important that you have the 

segments positioned correctly in the 

positioning part otherwise the products 

won’t vend properly and will cause jams

 

 

Correct Position: the two black pins are in 

the middle of the three clear pins. 

 

Incorrect Position: The two black pins over 

on either end of the three clear pins. 

If this is the case, you need to lift all the 

segment up and readjust the segments to 

the correct position. 

 

Replace the black centre part on to the 

machine and use a 9/16 wrench to 

secure the black centre part.  

 

Test the machine to make sure the 
segments are turning and that there are 
no issues. 

 

 

Replace the lid and lock the top lid of the 

tower using the Silver 100 Lid key a ¼ turn 

 

 

 

 

 

 

 

 

Summary of Contents for Vending Tower

Page 1: ...1...

Page 2: ...your order 3 Assembling tower with black stand 4 Optional Sticker placement 8 Opening the machine 11 Cardboard Backings 14 Adjusting the twist motion 15 Operating the machine 16 Replacing the plastic...

Page 3: ...g assembly to ensure all parts have arrived The larger tower box contains the Tubz Vending Tower a set of Silver 100 Lid Keys and a set of Black 002 Coin Box Keys Note Some tower units will arrive pre...

Page 4: ...tart by standing the post up so that the 4 square holes are facing up toward you Step 2 Flip the base upside down and lay it on top of the post making sure to line the square holes up with the holes o...

Page 5: ...r and one nut Step 4 Place on the Locking Washer and Nut then tighten with a 9 16 wrench Repeat 3 more times into all 4 Large Bolts are secure Step 5 Now flip the post and stand it upright Note The La...

Page 6: ...tower plate on top of the post Note May have to spin the tower plate to line up with the following holes Step 7 Once the holes are aligned screw in the 4 small bolts into the tower plate Tighten them...

Page 7: ...gether then the other two holes This Is important because the machine will only fit onto the post in certain direction So spin the tower until the holes are aligned Step 9 Now place the machine on top...

Page 8: ...will provide you a full set of stickers for your machine Note Some Towers will arrive pre stickered Step 2 The following are the recommended sticker placements Please also see Stickers guide Sheet Tu...

Page 9: ...brand stickers on each side of the machine lining up the middle of the sticker to the seam in photo The www ilovetubz com stickers are placed on the front of each machine between the segments and the...

Page 10: ...nsert 1turn twice stickers are placed on each side of the front mechanism align the bottom of the sticker with the top seam in photo The 3x lid stickers are placed side by side all the way around the...

Page 11: ...ing stuck The Silver 100 Lid Keys are for the Top Lid and the BLACK 002 Coin Box Keys are for the coin box Your set of vending machine keys includes 2 Black 002 Coin Box keys and 2 Silver 100 Lid keys...

Page 12: ...kes one quarter turn to remove the lid Step 2 To open the coin box simply unscrew the lock using the Black 002 Coin Box key This lock is a traditional style vending lock and requires you to turn until...

Page 13: ...ole in the coin drawer Next using the 2 small pegs turn the entire silver bar counter clockwise Now you can remove the entire silver bar Once you remove the coins simply slide the drawer back in pop i...

Page 14: ...ne for toys Step 2 Remove the top lid of the tower using the all silver key Now place the 9x cardboard backings into each machine s slot Note Notice the lip inside each of the slots make sure the back...

Page 15: ...ere Once you loosen the bolt a little no need to completely remove Grab onto all the plastic sections and pull down to add tension to the twist to choose action If loosening the tension no need to pus...

Page 16: ...n mechanism The product that is lined up is the product that will vend Step 2 Now that you have chosen the selection that you want Insert the 1 coin into the Coin Mech The Sweet toy Tower is currently...

Page 17: ...Use a 9 16 wrench to remove the black centre part Step 3 The tower machine is designed in sections so you can easily replace a broken section Step 4 When placing the sections back together rotate each...

Page 18: ...black pins are in the middle of the three clear pins Incorrect Position The two black pins over on either end of the three clear pins If this is the case you need to lift all the segment up and readj...

Reviews: