Installation.
Unless otherwise stated TSL equipment may be installed at any angle or
position within an operating temperature range of 5
°
- 30
°
C .
All TSL equipment conforms to the EC Low Voltage Directive:
EC Low Voltage Directive (73/23/EEC)(OJ L76 26.3.73)(LVD).
Amendment: (93/68/EEC) (OJ L220 30.8.93).
In all cases the frame of the equipment must be earthed on installation.
The earth pin on the IEC mains inlet connector is connected to the metal
frame of the equipment, to 0 volts on the internal DC PSU and to signal
ground, unless otherwise stated. All metal panels are bonded together.
Check that the voltage selector setting (if fitted) and the fuse rating is
correct for the local mains
supply.