TrinityHighway.com
23
Revision F November 2021
C. Place the CRP Cable Bracket (PN-33909G) on the threaded end. The angle end of
the bracket is placed up (See Figure 3).
D. Place a flat washer (PN-4902G) and hex nut (PN-4903G) on the threaded fitting on
the cable. Thread the nut approximately halfway on to it. Place on the fitting a second
hex nut up against the first nut
E. Perform Steps B-D for the other three (3) cables.
Option B (Field Cut Cables)
A. Cut four (4) lengths of cable from the cable reel.
B. Place a right-hand and left-hand field fitting (use the same size fittings used for line
cables) on the end of the cables. See the Field Splice section for assembling the
fittings.
C. Perform Steps A-D in Option A
except
for Step D if using 3/4” fittings, then replace
PN-4902G with PN-3701G and PN-4903G with square nut (PN-4959G).
Installing the Cables on the line terminal posts:
1. The CRP 1X cable attached to CRP 1X will use holes 3 and 4 on line terminal post 9;
holes 5 and 6 on line terminal post 8; and middle two (2) holes for posts 4-7.
2. The CRP 1 cable attached to CRP 1 will use the top two (2) holes of line terminal post 9;
holes 3 and 4 on line terminal post 8; and the top two (2) holes for post 4-7.
3. The CRP 2 cable attached to CRP 2 will use the bottom two holes on line terminal posts
4-9.
4. The CRP 3 cable attached to CRP 3 will use the middle two holes (holes 5 and 6) for line
terminal post 9; holes 7 and 8 on line terminal post 8; and bottom two holes on line
terminal posts 4-7.
5. The cables are attached to the posts using cable lock bolts (PN-5925G) (See Figure 5).
6. Insert the non-threaded end of the cable lock bolt in one of the two required holes and
place the cable lock bolt around the cable and insert the threaded end in the other
required hole (
either orientation of the cable lock bolt is acceptable
). Place a hex
nut (PN-3245G) on the cable lock bolt, and tighten until snug with a minimum of two
threads beyond the nut.
Line Cables
The cables used in the CASS
®
S3 System are pre-stretched. They are supplied on reels, either
precut with factory applied fittings (in 1,000’ [305 m] increments) or continuous length to be cut in the
field and field applied fittings attached. The reels can be supplied with 2,000’ to 3,000’ [610 m to 914
m] of cable on each reel. The precut cable has a right-hand fitting on one end and left-hand fitting on
the other end. The cables are placed on the reel with the left-hand fitting placed on the reel first. The
right-hand fitting end for the cable must come off first and the end is painted red for identification.
When there is more than one cable on the reel, the last cable placed on the reel will have the right-
hand fitting painted red and also a yellow mark. This will be the first cable removed from the reel.