6. FLUE DISCHARGE

To evacuate the products of combustion safely and
thoroughly, the boiler has a highly efficient integral flue
system and there is no need to fit the boiler to a separate
flue. See page 17 for flue fitting instructions.

INSTALLATION NOTES

a)

Trianco H.E. boilers operate at high efficiencies
with low flue gas temperatures. The flue system
used on this boiler is suitable for low flue gas
temperatures and condensation.

b) 

Ensure that all the joints on the flue system are
adequately sealed, and that no condensation can
escape. It may be necessary to apply a thin bead of
silicone sealant or other lubricating substance
around the flue joints and ‘o’-ring seals before
assembling the flue.

c) 

Only 28 sec. Kerosene class C2 to BS 2869 is
permitted for boilers using low-level flue discharge.

d) 

Positioning of flues under balconies and carports is
to be avoided

e) 

Modern low-level flue boilers are designed to operate at
low noise levels. However, when positioning you boiler,
it is not recommended to have the terminal facing a
neighbour’s property or patio, etc.

f) 

The boiler should also be positions to avoid the products
of combustion entering the building. A distance of at
least 600mm must be allowed between the terminal and
any window, door or other opening into the building (see

fig. 14

) for recommended terminal positions.

g) 

At certain times during operation, a plume of
condensation will be produced from the terminal. When
positioning the boiler, this should be taken into
consideration to ensure that it does not cause a
nuisance to neighbouring properties.

h) 

Keep the terminal clear of infra-red sensing devices,
such as those used to control security lighting.

i) 

The terminal must be protected by the guard supplied.

DIM ‘A’

Directly below an opening, air brick, window, etc.

600mm

Horizontally to an opening, air brick, window, etc.

600mm

Below a gutter, eaves or balcony with protection

75mm

Below a gutter, eaves or balcony without protection

600mm

From vertical sanitary pipework

300mm*

From an internal or external corner

300mm*

Above ground or balcony level

300mm*

From a surface or boundary facing the terminal

600mm

From another terminal facing the terminal

1200mm

Vertically from another terminal

1500mm

Horizontally from another terminal

750mm

* Scotland 1990

FIG 14

TERMINAL POSITIONS

All distances in millimetres, as measured to the

termination point or rim of low-level discharge

terminal.

Summary of Contents for Contractor H.E. 50/90 EXTERNAL

Page 1: ...1 H E 50 90 EXTERNAL HE 100 125 EXTERNAL OIL FIRED CENTRAL HEATING BOILER...

Page 2: ...2...

Page 3: ...y Siting System design Heating hot water systems Electrical supply Wiring diagram Condensate drain connections 5 OIL SUPPLY Oil Storage tank Single pipe oil supply Two pipe oil supply Oil de aerators...

Page 4: ...h programmer if fitted is set to the OFF position BOILER CONTROL THERMOSTAT The boiler control thermostat allows you to select the temperature of the water leaving the boiler It is calibrated between...

Page 5: ...empty before refilling as sludge and water could be sucked into the oil pipe affecting the operation of the burner and potentially reducing the life of the pump After a delivery of oil it is recommend...

Page 6: ...6...

Page 7: ...lly automatic in operation and incorporates all necessary safety controls to ensure safe and reliable running The Contractor H E External boiler is supplied with the burner set for 28 sec Kerosene Cla...

Page 8: ...8 3 TECHNICAL INFORMATION FIG 3 OUTLINE DIMENSIONS FIG 4 View of rear of boiler showing boiler connections Connections can be made on left or right side of boiler...

Page 9: ...TION Boiler shell insulated with glass fibre ELECTRICITY SUPPLY 230 280V 50Hz fused at 5 amp BURNER INFORMATION Model Output non condensing Output condensing Input Nozzle Pump Pressure CO2 50 000 BTUs...

Page 10: ...arance and Service Access When siting the boiler ensure adequate clearance is allowed for making water and flue connections As the boiler can be fully serviced from the front there is no need for head...

Page 11: ...cord 0 75mm 24x0 2mm code designation H05 VV F or H05 VVH2 F as specified in table 16 of BD 6500 All external cables entering the control box must be secured in position by the use of strain relief bu...

Page 12: ...ate pipework remove the inspection cover from the top of the condensing unit and pour a small amount of water inside Examine the condensate pipework for any resultant leaks and rectify accordingly Fai...

Page 13: ...r ventilation the wall must have at least a half hour resistance to fire and must extend 1 8 metres from any part of the tank Alternatively a non combustible radiation barrier can be employed which me...

Page 14: ...ine An additional flexible oil line is also required Notes 1 The pump suction should not exceed 0 4bar as dissolved gas may be released from the oil affecting combustion 2 The return pipe must end at...

Page 15: ...15 FIG 12 SINGLE PIPE OIL SUPPLY BOILER FIG 13 TWO PIPE OIL SUPPLY BOILER...

Page 16: ...ositions to avoid the products of combustion entering the building A distance of at least 600mm must be allowed between the terminal and any window door or other opening into the building see fig 14 f...

Page 17: ...face is to the inside 3 Smear a thin bead of silicone sealant supplied around the o ring seal and slide the terminal into the elbow from the outside of the boiler casing being careful to ensure that...

Page 18: ...is just before the start of the heating season Condensate Unit Trap The condensate unit and trap should be inspected as part of the annual service schedule Remove the access cover from the top of the...

Page 19: ...s within the condensate pipework and the U trap itself When complete recheck the integrity of the pipework joints by pouring a small amount of water into the condensate unit and looking for leaks Some...

Page 20: ...Press red reset button under control panel and check function of boiler stat Ensure all controls are calling for heat Fit new fuse 5A If problem persists check for short circuit in wiring Check for ro...

Page 21: ...nst settings shown in burner leaflet Raise tank or fir two pipe system Replace nozzle with one of same specification see burner leaflet Check pump pressure and adjust to settings shown in burner leafl...

Page 22: ...ess Cover 208803 1 208803 1 18 Burner 223868 1 223928 1 19 Burner Cover 223444 1 223444 1 20 Burner Cover Plate 223447 1 223447 1 21 Flexible Oil Line 2 207019 1 207019 1 22 Acoustic Hose 209491 1 209...

Page 23: ...23...

Page 24: ...24 April 2007 Item No 223839 Issue No 1 Fax 0114 257 1419 TRIANCO HEATING PRODUCTS LTD Thorncliffe Chapeltown Sheffield S35 2PH Tel 0114 257 2300 Fax 0114 257 1419 www trianco co uk...

Reviews: