USE TREX TRANSFORMER ONLY. Use of any other

 

transformer voids warranty.

Planning

 NOTE: 

When designing your deck, plan locations of 

lights, power supply, timer, and dimmer. These should 
be accessible for service. Installing a GFCI outlet is 
REQUIRED to help prevent damage to lighting from 
electrical surges.

1.  The dimmer remote will work in

a 30' (9 m) radius of the unit.

2.  Dimmer should be installed in a

dry location.

3.  Timer must be installed

vertically with receptacle facing 
downwards. Timer must be at 
least 1' (.305 m) from ground 
level when installed as per 
federal safety code height regulations. Timer must be 
in view of the sun to use the dusk/dawn feature.

Installing Wiring

NOTE:

 It is recommended to install wiring and splitters 

before decking and railing have been installed.

»  Use male-to-male connection wire (lengths vary)

that will connect to each required splitter.

1.  Wiring must be run under

decking structure and
behind stringers. 

DO NOT

run wires between deck
boards and joists. Staple
to frame with cable staples
at least 1/4

"

 (6 mm) wide.

DO NOT

 crush wire

insulation with staples.

2.  Wiring can be run under deck and behind risers.

Staple to frame with cable staples at least 1/4

"

(6 mm) wide. 

DO NOT

 crush wire insulation with

staples.

3.  Remove 5' (1.52 m) lead wire that is connected to post

cap and attach wire to post with male connection at
top of post (female connection would be at bottom of
post and connect into splitter). Avoid running wire on
side of post where railing brackets or deck rail lights
will be installed. Leave approximately 6

"

 (152 mm) of

lead at top to make connections. Staple to frame and
posts with cable staples at least 1/4

"

 (6 mm) wide.

DO NOT

 crush wire insulation with staples.

Making Connections

1.  Install splitters to

inside of framing using
hardware provided.
Install at every post
base where lighting is
present and depending
on spacing in between
each riser and recessed
light.

2.  Attach male lead from lights to female connections

on splitter. Also attach male-to-male connection
wires in between each splitter. Continue until all
wiring from lights are attached to splitters and
connector wires are attached in between splitters.

3.  Cap off all unused female connections on splitters

using caps provided or weather-resistant silicone.

GFCI 

Outlet

Timer

Transformer

To Splitter

Dimmer

(Optional)

1

3

6"

(152 mm)

1

1

2

2

Light

connection

Connection 

wire

Connection wire

3

2

TRANSFORMER CAPACITY BY TYPE

8.3A Transformer 

(83 DL TRANSFORMER)

Type of

Light

2.5A Transformer 

(2.5 DL TRANSFORMER)

Riser  

285  

90

Recessed  

285 

90

Post Cap 

85 

22

Deck Rail 

285 

90

Above listing is for maximum number of each individual types of lights. 
If mixing and matching lighting, contact Trex to determine if more than 
one transformer is required.

HOW TO INSTALL TREX DECKLIGHTING/

CONTINUED

2

www.SolarPostCapsDirect.com  |  (800) 878-7829  |  [email protected]

Summary of Contents for DeckLighting

Page 1: ...ly premature fixture failure and is not covered by the Trex limited warranty You must use a Trex transformer on all Trex lighting installations Never fully drive staples when securing wire Wire should move under staple ALWAYS protect any wire that is close to the ground with conduit or wire loom to prevent rodent damage Cap all unused female connections with caps provided or weather resistant sili...

Page 2: ...d attach wire to post with male connection at top of post female connection would be at bottom of post and connect into splitter Avoid running wire on side of post where railing brackets or deck rail lights will be installed Leave approximately 6 152 mm of lead at top to make connections Staple to frame and posts with cable staples at least 1 4 6 mm wide DO NOT crush wire insulation with staples M...

Page 3: ...red height centered on post sleeve for deck rail light location NOTE If deck boards are not installed yet place a deck board on framing to ensure post sleeve is at correct height 2 Drill a 1 25 mm hole through post sleeve Drill deep enough to mark location on pressure treated post 3 Remove the post sleeve from the post 4 Drill out existing hole on pressure treated post 3 4 19 mm deep Drill two add...

Page 4: ...itter Also attach male to male connection wires in between each splitter Continue until all wiring from lights is attached to splitters and connector wires are attached in between splitters See Making Connections section for details NOTE DO NOT install riser light or deck rail light into top or bottom rails or balusters Installing Recessed Deck Lights NOTE Install recessed deck lights after instal...

Reviews: