Installation
(for qualified installers only)
7
© Travis Industries
4140221
100-01345
Packing List
Propane Conversion Kit
Log
Set
Firestop (sku 250-00747)
Remote
Additional Items Required
Direct
Vent
Gas Line Equipment (shutoff valve, pipe, etc.)
Electrical Equipment (min. 14 gauge, grounded line)
Installation Overview
All requirements below must be met.
Recommended Installation Procedure
Frame the opening for the fireplace. Make sure to allow for vent installation.
This fireplace is designed to accommodate 1/2" (13mm) or 5/8" (16mm) drywall (see "Nailing
Brackets" on page 15 for details). Secure the fireplace to the framing.
Install the vent, gas line and electrical hook-up.
Install the drywall.
Install the hearth (if applicable).
Install the facing (if applicable).
Install the mantel (if applicable).
Finalize the installation (see page 43) and install the grill or face.
See the section
"Approved Vent
Configurations"
See the section
"Electrical Connection"
See the section
"Mantel Requirements"
Insulation must not fill
the 1/2" (13mm)
clearance around the
back and sides of the
fireplace.
See the section
"Vent Requirements"
See the section "Minimum
Framing Dimensions"
Drywall
Top Vent
Configuration
Rear Vent
Configuration
See the section
"Gas Line Installation"
Side
Wall
See "Optional Non-
Combustible Facing"
Drywall
See "Optional Non-
Combustible Hearth"
Nailing Brackets
Required Travis
Firestop (sku
250-00747)
1" Min.
25mm