background image

Piping

18

 CLCH-SVX08C-EN

Proper Gas Pressure

To assure sufficient gas pressure at the unit, use 
appropriately sized gas pipe for unit capacity. Refer to 
the National Fuel Gas Code for pipe sizing information.

Select an appropriately sized gas pressure regulator to 
assure the required gas supply pressure is maintained 
at the unit.

Required gas pressure to the gas train is 7 to 14 inches 
wc (0.25 to 0.5 psig) for units through 2400 MBh. Note 
that a minimum of 9 inches wc (0.32 psig) is required 
for 1250-2000 MBh heaters with 10:1 turndown 
capability. For all size units, do not exceed 14 inches wc 
(0.5 psig) inlet gas pressure.

Gas pressure and volume must be maintained and 
stable at high fire.

If the gas pressure regulator serves more than one 
heating unit, it must be sized appropriately to ensure 
that the inlet gas pressure at each unit is 7 to 14 inches 
wc while all burners are firing. Nine inches wc is 
required for 1250 to 2000 10:1 turndown heaters. Gas 
pressure must not exceed 14 inches wc when all units 
are off.

Check the gas supply pressure before making the final 
connection to the unit. If the gas pressure is too high, 
damage to the gas valve could occur.

Heat Exchanger Condensate 
Piping

Condensate usually does not form in the heat exchanger 
during normal heating operation. However, if the unit 
operates for extended periods of time at very low fire, or 
if the air handler serves as a cooling unit also, condensate 
can form in the heat exchanger and should be removed.

All units are equipped with a condensate drain and drain 
valve. The condensate drain is on the same side as the gas 
train located inside the piping vestibule.

Since the drain line is equipped with a shut-off valve, a 
condensate p-trap is not required, but may be installed for 
convenience to avoid periodic manual draining. If a p-trap 
and drain is to be connected to the condensate drain line, 
consult local plumbing codes for disposal of the 
condensate may be a slightly acidic solution. 

Use 

Figure 15

 as a guideline for p-trap construction.

The use of a tee-fitting at the connection to the condensate 
outlet is recommended. This allows for priming and 
cleaning the trap. If a tee-fitting is used, be sure to furnish 
a plug or cap for the clean out opening. Be sure to replace 
the plug after priming or cleaning the trap.

Figure 14.

Gas heat external piping penetration 
location 

NOTICE

Excessive Gas Pressure! 

The gas pressure at the inlet to the gas train must not 
exceed 14 in. wc. A properly sized gas regulator that 
provides a maximum of 14 in wc. of gas pressure, must 
be supplied in the gas inlet line to unit. Failure to 
maintain proper gas pressure could result in damage to 
the gas train components. 

Combustion Air Inlet

Shaded area is "OK" for gas inlet pipe
Do not install gas pipe in access door or combustion air inlet

Access
Door

Access
Door

Flue

External Vestibule

Combustion Air Inlet

Combustion Air 
Vented Floor Inlet 

Table 6.

Gas supply line connection sizes

Gas Output (MBh)

200-320

(Midco Burner)

200-560 

(Non-Midco Burner)

700-1000

1250-1750

2000-2400

Connection Size (NPT)

3/4 in.

1 in.

1 1/4 in.

1 1/2 in.

2 in.

Note:

If gas output is between 200 and 320 MBh, confirm burner manufacturer before sizing gas supply line.

Figure 15. Heat exchanger condensate piping

L = H + J + diameter where:

H = 5 inches

J = 2.5 inches

L

H

J

Tee with cap

Normal operation

Shut-off Valve

1/2” NPT

Summary of Contents for K01K12345

Page 1: ...training Improperly installed adjusted or altered equipment by an unqualified person could result in death or serious injury When working on the equipment observe all precautions in the literature and...

Page 2: ...n which if not avoided could result in minor or moderate injury It could also be used to alert against unsafe practices NOTICE Indicates a situation that could result in equipment or property damage o...

Page 3: ...ion sizes for gas heat sections figure in Installation chapter Updated Duct Connection section in Installation chapter Added Gas heat internal piping penetration location and Gas heat external piping...

Page 4: ...stalling Outdoor Flue Stacks 14 Installing Indoor Flue Stacks 15 Installing Rain Hood Combustion Air Inlet 15 Installing Flue Stack for Hurricane Applica tions 15 Duct Connections 16 Combustion Air Du...

Page 5: ...handler section includes a nameplate label see Figure 1 which identifies the type of section customer tagging information the unit serial number the unit order number the build section position for in...

Page 6: ..._________________________________________ Altitude Above Sea Level___________________________________________________________________ Calorific Value___________________________________________________...

Page 7: ...gure 2 The external vestibule if required ships attached to the gas heat section Some heaters have gas train components in an internal vestibule see Figure 3 Refer to Table 2 for vestibule locations F...

Page 8: ...25 560 Ext 50 1750 Ext 120 1000 Int 25 700 Ext 50 2000 Ext 120 1250 Int 25 860 Ext 57 560 Int 120 1500 Int 25 1000 Ext 57 700 Int 120 1750 Int 30 320 360 Int 57 860 Int 120 2000 Int 30 560 Int 57 100...

Page 9: ...removed before assembly to the air handler Instruction Manuals Individual instruction manuals for all of the gas train components such as flame control relay valves pressure switches and actuators sh...

Page 10: ...or units that will be installed indoors However when outdoor storage is necessary several things must be done to prevent damage Note Keep the equipment on the original wooden blocks skid for protectio...

Page 11: ...ltage panel 61 61 61 61 61 61 61 61 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 D internal starter or VFD 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 E fan 48 48...

Page 12: ...75 85 50 92 50 107 50 119 75 119 75 Width 93 50 100 00 112 50 125 50 125 50 140 50 140 50 154 50 182 00 Height for outdoor unit includes base drip lip b 69 25 75 00 75 00 84 38 94 13 97 63 112 63 124...

Page 13: ...o the gas heat system if thesupply fan isshut off The gas heat system must not operate without the supply fan providing airflow All wiring must comply with applicable local and National Electric Code...

Page 14: ...ove the flue from inside the unit once the unit is assembled Installation High Altitude Installations Adjustment of gas train linkages is not normally required However for high altitude installations...

Page 15: ...r the combustion air opening ship loose and must be installed at the job site The assembly consists of the hood butyl tape and number 10 screws Install butyl tape between the hood and the side panel o...

Page 16: ...additional static pressure of the inlet air duct may change the fuel air ratio slightly necessitating system adjustment Separated combustion can be a desirable option but will require more field insta...

Page 17: ...on and Deadly Gases Never solder braze or weld on refrigerant lines or any unit components that are above atmospheric pressure or where refrigerant may be present Always remove refrigerant by followin...

Page 18: ...he same side as the gas train located inside the piping vestibule Since the drain line is equipped with a shut off valve a condensate p trap is not required but may be installed for convenience to avo...

Page 19: ...ield wiring poses FIRE and ELECTROCUTION hazards To avoid these hazards you MUST follow requirements for field wiring installation and grounding as described in NEC and your local state electrical cod...

Page 20: ...power the transformer TRANS1 Low Voltage Wiring The gas heat control system requires a binary signal for on off control Provide an interlock in the start stop signal circuit with the air handler supp...

Page 21: ...Wiring CLCH SVX08C EN 21 Figure 16 Natural gas 200 320 MBh 10 1 turndown...

Page 22: ...Wiring 22 CLCH SVX08C EN Figure 17 Natural gas 360 1000 MBh 3 1 and 10 1 turndown and propane 200 1000 MBh...

Page 23: ...Wiring CLCH SVX08C EN 23 Figure 18 Single phase natural gas and propane 1250 2000 MBh 3 1 and 10 1 turndown...

Page 24: ...Wiring 24 CLCH SVX08C EN Figure 19 3 Phase propane and natural gas 1250 2000 MBh 3 1 and 10 1 turndown with power exhaust...

Page 25: ...Wiring CLCH SVX08C EN 25 Figure 20 Natural gas and propane1250 2400 MBh 20 1 turndown...

Page 26: ...w g Attach another manometer to the burner manifold if optional gauge or sensor is not selected to check the burner manifold pressure when the unit is operational Typical pressure should be between 2...

Page 27: ...er assembly The following safety limit contracts should be closed HLl1 high temperature limit Al1 airflow interlock air handling fan should either be running or started 60 seconds after call for heat...

Page 28: ...ignition transformer and automatic gas valves will energize With the manual gas cocks closed the burner should go into a safety lockout condition The flame safeguard will have to be reset manually Tur...

Page 29: ...luminate The modulating gas valve actuator starts to open and the main light on the flame relay module should illuminate Note that it could take as long as 30 seconds for the actuator to fully open 6...

Page 30: ...d drain any accumulated condensate 3 Check all electrical terminals for tight connections 4 Open all manual gas valves and ensure that these valves operate freely 5 Check the air shutter and modulatin...

Page 31: ...densate from heat exchanger Weekly This task only needs to be done if the unit runs for extended hours at low fire Clean air inlet louver Monthly Use brush and vacuum cleaner Clean combustion air blow...

Page 32: ...gh Limit This switch trips due to a high temperature condition in the gas heat section Allow the air handler fan to run and cool heat exchanger The switch must be manually reset when the heat exchange...

Page 33: ...quate grounding and that it is properly located in the flame Also ensure that temperature at flame rod insulator is no greater than 500 F 260 C Perform Ignition Interference Test per component manufac...

Page 34: ......

Page 35: ......

Page 36: ...and protect food and perishables and increase industrial productivity and efficiency We are a global business committed to a world of sustainable progress and enduring results ingersollrand com Ingers...

Reviews: