6. Check pulley alignment.
•
•
•
Place a straight edge across pulleys faces to correct
alignment.
Check parallel position of shafts and correct alignment
or grooves.
Note: Store belts in a cool, dry place out of direct
sunlight.
Types of sheave and shaft misalignment
Horizontal Angular
Vertical Angular
Parallel
Align with straightedge along
sheave faces
Figure 18
Sheave Alignment
Figure 19
Belt Tension
Measurement
Note: Fan belt tension should be checked at least twice during
the first day of operation, since there is a rapid decrease in
tension until belts are run in. Proper belt tensioning is required
to ensure maximum bearing and drive component life and is
based on fan brake horsepower requirement.
Check the belt tension as follows:
Measure the span length mm of the drive. With a belt
tensioner at the center of the span, apply a force K
(perpendicular to the span) large enough to deflect the belt
15mm per 1 meter of span. Refer to figure 19.
The deflection force for the belt should be within the minimum
and maximum force shown in the Table 3. When the tension
drops to the minimum value, re-adjust to the maximum value.
To measure belt tension, use a belt tensioner as shown in
figure 20. Determine the actual deflection by depressing one
belt with the belt tensioner and measuring the deflection
relative to the other belts or to belt line. Adjust the belt tension
to the correct force (Newton) and tighten all setscrews to the
proper torques.
Fan Belt Tension
Belt Tension Measurement
Summary of Contents for CLCP Euro 25
Page 18: ...Assembly Installation CLCP EURO CLCP EURO XP Paneling 18...
Page 22: ...Assembly Installation CLCP EURO XP CKD At Jobsite 22...
Page 23: ...23 Assembly Installation CLCP...
Page 24: ...Assembly Installation CLCP 24...
Page 40: ...Maintenance 40 Figure 20 Belt Tension Measurement...
Page 42: ...Trouble Analysis 42...
Page 43: ...43 Trouble Analysis Pulley and Belt...
Page 44: ...Appendix A Fan and Arrangement 44 Fan Discharge Arrangement...
Page 51: ...Typical Motor Wiring Diagram 51...
Page 52: ...52 Service Light and Door Switch Wiring...
Page 53: ...Factory Installed VFD TR200 Wiring Setting 53...
Page 54: ...Factory Installed VFD TR200 Wiring Setting 54 TR200 BASIC SETTING_OPEN LOOP...
Page 56: ...Pre Start Up Checklist 56...
Page 57: ...Pre Start Up Checklist 57...