Failure to follow instructions below could result in death
or serious injury.
• All Ingersoll Rand personnel must follow Ingersoll
Rand Environmental, Health and Safety (EHS)
policies when performing work such as hot work,
electrical, fall protection, lockout/tagout, refrigerant
handling, etc. All policies can be found on the BOS
site. Where local regulations are more stringent
than these policies, those regulations supersede
these policies.
• Non-Ingersoll Rand personnel should always follow
local regulations.
WARNING
Follow EHS Policies!
Copyright
This document and the information in it are the property of
Trane, and may not be used or reproduced in whole or in part
without written permission. Trane reserves the right to revise
this publication at any time, and to make changes to its content
without obligation to notify any person of such revision or
change.
Trademarks
Revision History
All trademarks referenced in this document are the
trademarks of their respective owners.
Introduction
3
Summary of Contents for CLCP Euro 25
Page 18: ...Assembly Installation CLCP EURO CLCP EURO XP Paneling 18...
Page 22: ...Assembly Installation CLCP EURO XP CKD At Jobsite 22...
Page 23: ...23 Assembly Installation CLCP...
Page 24: ...Assembly Installation CLCP 24...
Page 40: ...Maintenance 40 Figure 20 Belt Tension Measurement...
Page 42: ...Trouble Analysis 42...
Page 43: ...43 Trouble Analysis Pulley and Belt...
Page 44: ...Appendix A Fan and Arrangement 44 Fan Discharge Arrangement...
Page 51: ...Typical Motor Wiring Diagram 51...
Page 52: ...52 Service Light and Door Switch Wiring...
Page 53: ...Factory Installed VFD TR200 Wiring Setting 53...
Page 54: ...Factory Installed VFD TR200 Wiring Setting 54 TR200 BASIC SETTING_OPEN LOOP...
Page 56: ...Pre Start Up Checklist 56...
Page 57: ...Pre Start Up Checklist 57...