background image

ACC-SVN44D-EN

9

Installation

Factory Installed Economizer Set-Up 

Downflow Configuration

To position economizer for Downflow operation, complete the following steps:

WARNING

Hazardous Voltage!

Disconnect all electric power, including remote disconnects before servicing. Follow proper 
lockout/tagout procedures to ensure the power can not be inadvertently energized. Failure to 
disconnect power before servicing could result in death or serious injury.

1.

Remove filter access panel.

2. Remove bottom blockoff from its shipping location. See 

Figure 9

.

3. Remove the bottom three screws from the economizer panel. 

4. Pull the economizer assembly out into operating position as shown in 

Figure 10

.

5. Secure the economizer assembly with 2 screws at the bottom of the corner posts.

6. Install bottom blockoff and secure with 3 screws.

Figure 9.

Figure 10.

Summary of Contents for BAYECON085A

Page 1: ...Number Used With BAYECON085A TSC YSC036E 060E R WSC060EDR THC YHC036E R WSC036E 048E R BAYECON086A THC YHC036E E TSC YSC036E 060E E BAYECON087A THC YHC048E 120E R WSC060E 3 4 W R TSC072E 120E R WSC07...

Page 2: ...r Act Section 608 sets forth the requirements for handling reclaiming recovering and recycling of certain refrigerants and the equipment that is used in these service procedures In addition some state...

Page 3: ...Installation 5 Horizontal Installation 5 Optional Sensors ReliaTel Only 6 Blockoff Asssembly 6 Wiring Connections ReliaTel Units 8 Electromechanical Units 8 Factory Installed Economizer Set Up 9 Down...

Page 4: ...nd WSC072 120E 1 Sensor Thermistor 1 Grommet 1 Tie Wire 1 Barometric Duct Blockoff Plate Installation Field Installed Note This instruction covers installation of BAYECON085A BAYECON086A T YSC036 060E...

Page 5: ...from bottom of panel for use later Downflow Installation For Downflow Installation assemble end panel to the economizer Refer to Figure 2 Horizontal Installation For Horizontal Installation assemble e...

Page 6: ...ctions provided in the kits Blockoff Asssembly The return duct blockoff plate s must be installed prior to the installation of the economizer in the unit Refer to Figure 5 for installation in units wi...

Page 7: ...e bottom of the economizer and secure bottom left 3 screws Remove the filter access panel Position the adapter backing plate inside the filter section The adapter backing plate will slip over the 3 sc...

Page 8: ...otor Note If Options Module RTOM is not installed then connect plug 3P4 to 3J4 on the Refrigeration Module RTRM in the control box Electromechanical Units Locate unit wiring harness plug PPM2A and plu...

Page 9: ...the power can not be inadvertently energized Failure to disconnect power before servicing could result in death or serious injury 1 Remove filter access panel 2 Remove bottom blockoff from its shippin...

Page 10: ...BAYENTH005A and BAYENTH006B install them now Use the instructions provided in the kits 7 Remove supply and return duct covers from the horizontal openings and install over the downflow opening 8 To r...

Page 11: ...when the blower circuit is de energized Dry Bulb Settings Standard economizer dry bulb changeover is field selectable to 4 outdoor temperatures See the following table for potentiometer settings The...

Page 12: ...vember 2009 The manufacturer has a policy of continuous product and product data improvement and reserves the right to change design and specifications without notice Only qualified technicians should...

Reviews: