9 Checklist
We recommend that you work through the checklist during commissioning and when replacing the
measuring system and store it as part of the overall system documentation.
Documentation basis
Date
Edited
Checked
Sub-item
To note
Can be found under
yes
Present user manual has been read
and understood
–
Document no.: TR-ECE-BA-GB-0120
Check that the measuring system
can be used for the present
automation task on the basis of the
specified safety requirements
●
Intended use
●
Safety functions of the fail-safe
processing unit
●
Compliance with all technical data
●
Chapter
●
Chapter
Safety functions of the fail-safe
●
Chapter
Fulfillment of the installation
requirements
●
Connection of the measuring system
- shaft to the drive must be designed
as form closure
●
The coupling to the drive must be
over-dimensioned in accordance with
DIN EN 61800-5-2:2014-06 - Draft
●
Chapter
Voltage supply requirement
●
The power supply used must meet
the requirements of SELV/PELV
(IEC 60364-4-41:2005)
●
Chapter
Electrical characteristics, page 20
●
Chapter
Correct electrical installation
(shielding)
●
Observance of basic rules for
installation
●
Observance of wiring standards
●
Chapter
Installation / Preparation for
System test after commissioning
and modifications
●
During commissioning and after any
modifications all affected safety
functions must be checked
●
Chapter
Safety functions of the fail-safe
Device replacement
●
It must be ensured that the new
device corresponds to the replaced
device
●
All affected safety functions must be
checked
●
Chapter
Replacing the Measuring System,
●
Chapter
Safety functions of the fail-safe