background image

Magquickstart1_ver3  

TOSHIBA INTERNATIONAL CORPORATION

 

 

 

 

 

 

 

 

 

 

 

Magmeter Quick Start 

  

Guide  

 

 

 

 

 

 

 

 

 

 

NOTE: CHECK THE OPERATION MANUAL FOR SAFETY AND STORAGE 

PRECAUTIONS BEFORE INSTALLATION!! 

Summary of Contents for GF632

Page 1: ...Magquickstart1_ver3 TOSHIBA INTERNATIONAL CORPORATION Magmeter Quick Start Guide NOTE CHECK THE OPERATION MANUAL FOR SAFETY AND STORAGE PRECAUTIONS BEFORE INSTALLATION ...

Page 2: ...ation 2 II I Procedure 3 III Additional Set up if required 6 III 1 Totalizer 6 IV Verification Check 7 IV 1 Procedure 7 i Appendix A 8 A Magmeter Operation Preparation 8 B Magmetger installation Connection 9 C Mag Connect 11 D DO Connect 12 Magquickstart1_ver3 ...

Page 3: ...h the E terminal on the converter and the detector With proper grounding of detector E terminal can be left un connected Additional information is given in the magmeter installation and Mag connect application notes See Appendix A A combine style magmeter only need to be installed and power applied II Configuration All remote style converters have to be configured in the field They are ship from t...

Page 4: ...f the box 11 1 Procedure After converter has been connected and power up hold finger over the center key for 3 seconds or longer cover don t have to be removed and enter code a series of arrows displayed on the screen if code is not entered correctly unlocking failure error will be displayed and after three 3 failed attempts unit will resort to the measurement screen After correct code is entered ...

Page 5: ...4 At the first menu A DECTECTOR press enter Select EXC CUR and press enter default 0 2000 A Set right excitation current for detector note 3 ...

Page 6: ...nter default 6 in Set correct meter size and verify excitation frequency under the EXC FREQ option note 4 Next go to menu C RANGE and press enter Select R1 and press enter default 2500 gal min Set desired range for meter note 5 ...

Page 7: ...refore there is no need to set but one can always verify Note 5 Range Type is default at SINGLE but can be change if other flow options are required Also when there is a meter size change from the default or otherwise the range value will be change to m s When changing to gal min it is necessary to change units first then set correct range value III Additional Setup if required III I Totalizer Cou...

Page 8: ...e see appendix A When COUNT is chosen as a unit for totalizer display and totalizer reaches its maximum value 99999999 it will automatically roll over and reset itself if any other unit is chosen such as gal totalizer have to be manually reset when it reaches its maximum value IV Verification Check After converter and detector connected and unit powered up and configured a verification check of th...

Page 9: ...luid go through the detector pipe When the detector is filled with the fluid stop the fluid and keep it still in the detector pipe and prepare to do a meter zero Power supply Make sure the power supply is as specified Checking converter parameters Check the configuration parameter settings refer to instruction manual Zero Adjustment Warm up flow meter for 30 minutes Make sure the fluid holds still...

Page 10: ...re in instruction manual Note Cable length may not exceed 300m The allowable cable length between the detector and the converter depends on The electrical conductivity of the object fluid see chart in spec sheet The signal cable is a double shielded cable i e both conductors are individually shielded and the overall cable is also shielded Locate it as far as possible from other large current carry...

Page 11: ...tor at site e g pit installation ground the detector by connecting the E terminal of the detector to the E terminal of the converter using a 3 core cable The E terminal of the converter is connected internally to the FG terminal and the converter case If the pipeline is not of conductive material GROUNDING RINGS MUST BE USED If converter is being installed outdoors or in an area where it might be ...

Page 12: ... 3 SOOW rubber covered Cable LF6 or LF4 Series Note 4 20 Ma signal should have shield grounded on the receiving end only Note Terninal G is not ground It is an input to the measuringcircuit Toshiba Meters Source the 4 20 signal Converter Setup for RemoteInstallation All remote converter installations require that Menu A be setup in the field Excitation Current from meter tube MUST be set in A1 and...

Page 13: ...12 D DO Connection for Magmeter Note 7 Refer to operation manual for complete DI DO connection diagram ...

Reviews: