background image

g218544

Figure 1

1.

Roller shaft

7.

Flat washer

2.

Ball stud

8.

Spacer

3.

Ball-joint receiver

9.

Bushing

4.

Jam nut

10.

Pull-link assembly

5.

Pull-link extension

11.

Anti-scalp roller

6.

Bolt

2.

Remove the bolts and roller shafts securing the
anti-scalp rollers and the pull-link assemblies to
each carrier frame (

Figure 1

).

3.

Disassemble the pull-link assemblies (

Figure 1

).

4.

Thread the previously removed jam nut onto
each of the new longer pull-arm extensions
and onto the existing pull-link and bushing
assemblies (

Figure 2

)

g218546

Figure 2

1.

Roller shaft

9.

Spacer

2.

Ball stud

10.

Bushing

3.

Ball-joint receiver

11.

Pull-link liner

4.

Jam nut

12.

Pull-link assembly

5.

Long pull-link extension

13.

Link bracket

6.

Carriage bolt

14.

Bolt (3/8 x 1-1/2 inches)

7.

Locknut

15.

Anti-scalp roller

8.

Flat washer

5.

Assemble the new longer pull-arm extensions to
the existing pull-link assemblies and ball-joint
receiver assemblies (

Figure 2

). Do not tighten

the jam nuts at this time.

6.

Mount the appropriate link bracket (left or right)
and a previously removed anti-scalp roller to
the end of each front carrier frame with a new
carriage bolt and the previously removed roller
shaft. Position the brackets as shown in

Figure

2

.

7.

Mount a pull-link assembly to the outside of each
link bracket with a bolt (3/8 x 1-1/2 inches), flat
washer, bushing, the previously removed spacer
and flat washer, and a new locknut (

Figure 2

).

Note:

Make sure that the bushing is inside the

pull-link assembly.

8.

Slide back the sleeve on the ball-joint receivers
and install the receivers onto the ball studs
(

Figure 2

).

9.

Mount a basket onto the carrier frame.

10.

Adjust the pull arms until there is a 6 to 10 mm
(1/4 to 3/8 inch) clearance between the lip of the
basket and the reel blades.

2

 