Overall structural inspection :
check all components and trusses to ensure the entire structure
is rectangular as specified in (picture 1). All trusses must be 90 degrees straight up from the
container.
Secure and tighten all bolts and nuts on this step. But do not over tie! Otherwise you might
damage the tubes or components.
Step 6 : Install the cover
Pass the tie down straps (#9) through the top cover and tie it to the top cover tension tube and
pass the other end through the ratchet, adjust the ratchet to tighten. Pull the front cover and back
cover and tie them to the truss. All four sides must be firmly tied together at the same time to
ensure that it is square, smooth and straight. All grommets need to be fixed to the frame with
wavy lines. Finally, install the waterproof plugs to both ends of the top cover tension tube (see
picture 6 and picture 7 below).