8
Install the Flue
E.
1.
Remove the Flue from the packaging. Then, remove all protective film from the flue.
2.
Install the flue at the back of the unit by pushing it down, while fitting and aligning on both
sides.
Gas Connection
F.
1.
Only qualified and/or authorized persons must carry out the gas connection, testing and
commissioning of this equipment.
2.
After installing all the necessary parts, position the equipment in its final operating position.
3.
Before connecting the gas supply line to the equipment, check the following:
a.
Check gas type that will be supplied to the equipment. It should match the gas type
indicated on the rating label.
b.
Check the gas supply pressure. It should match the equipment’s required gas supply
pressure indicated on its rating label. Ensure that adequate supply pressure exists.
4.
When a supply regulator is to be installed, ensure that the supply regulator is converted to the
correct gas type that the equipment will operate on. Ensure that adequate supply pressure
and manifold pressure exists.
5.
It is recommended that an isolation valve be placed between the equipment and the main gas
supply line.
6.
Connect the main gas supply to the equipment. Unless compression fittings are used, it is
essential that a suitable joining compound which resists the breakdown action of LPG or
Natural Gas, must be used on every gas line connection.
7.
After connecting the main gas supply to the equipment, check all gas connections for leakages.
Check also for gas leakages those gas lines and gas connections that were disturbed during
installation. Use soapy water (bubble check), or any gas leak detecting solution. Do not use
naked flame to check for gas leaks.
Flue