A-weighed noise level
< 70 dB (A)
7. Transport and storage
7.1 Transport
When the machine needs to be moved, Thermopatch recommends to use the original
packaging.
7.2 Storage
When the machine needs to be stored, Thermopatch recommends to use the original
packaging. The machine should preferably be stored on a pallet, off the floor, in dry
conditions.
8. Maintenance
8.1 Daily maintenance
For good heat sealing results it is important to keep the press surfaces clean. Therefore,
clean the teflon coating of the upper plate with a clean, dry cloth.
Also clean the rubber pads daily with a dry cloth. Do not use solvents or other chemical
substances to remove impurities.
Do not let buttons, zippers, etc. come between the plates. It will keep the silicone rubber
undamaged for a long time.
8.2 Periodical maintenance
The mechanism needs no maintenance.
First switch off the machine, let it cool down and pull the plug out of the socket.
Replace the rubber pads and the teflon regularly.
Clean the outside of the machine regularly with a clean, moist cloth.
In order to replace the teflon, the press machine must be warm (± 80°C). Remove the
teflon and carefully remove all glue residues from the metal surface with a putty knife.
Then use a copper brush to clean the surface.
Finally, use a dry cloth to clean the element. The surface must be absolutely clean and
smooth, so that the new teflon sticks well, without air bubbles.
Summary of Contents for HS-21-SQR Penguin
Page 1: ...Y600 Thermo Seal Jet thermopatch com HS 21 SQR Penguin Manual September2020ENG...
Page 15: ...thermopatch com 15...
Page 17: ...thermopatch com 17...
Page 19: ...thermopatch com 19...
Page 21: ...thermopatch com 21...
Page 23: ...thermopatch com 23...