9
Adding Modules
Adding a SSL, SSLBKF, PTV, or PTVBKF Injector Module
422
TRACE 1300 and TRACE 1310 Hardware Manual
Thermo Scientific
Adding a SSL, SSLBKF, PTV, or PTVBKF Injector Module
This section provides instructions for adding a front/back SSL, SSLBKF, PTV, or PTVBKF
injector module. According to the configuration of your TRACE 1300/TRACE 1310, a
dummy module is present into the free site where the injector module is not installed.
See
Figure 438.
Add a New Front/Back Injector Module
To add an SSL, SSLBKF, PTV, or PTVBKF injector module
1. Put the GC in standby condition.
2. Cool the oven, injector, and detector to room temperature.
3. Close the gas supplies.
4. Power off the GC.
a.
Push down the power switch (breaker), located at the back of the instrument, to the
position O.
b. Unplug the power cable from the AC Input connector into the back of the GC and
from the wall outlet.
5. If external modules are present, unplug the power cable from the AC Input connector of
each external module, and from the wall outlet.
Dummy Front Injector Module
Dummy Back Injector Module
ATTENTION
Where a dummy module is installed, the gas connection is blocked by a
plug.
Note
By pressing the
Maintenance
button, the GC cool down is automatically
carried out.