WIRING REQUIREMENTS 

Pre-plumb wiring requirements are as per the diagram at the back of these instructions. 

The factory assembled pre-plumb wiring detail is shown to the lower section of the connector block complete with the plug in connector 
detail. 

The upper section of the wiring to the connector block depicts connections to be created by the installer. 

SYSTEM FILLING & COMMISSIONING 

Once all plumbing and wiring is complete the primary system may be filled and flushed in the proprietary manner. Before filling ensure all 
drain points and air valves etc. are fully closed. Fill via the filling loop ensuring the 2 port valves and the circulating pump isolation valves 
are fully open. 

Release all air from the auto air valve at the highest point of the pre-plumb pipework and also any other high points in the system. The 
normal fill pressure is 1.0 bar to 1.5 bar - check both the boiler and radiator manufacturers requirements. During filling ensure all plumbing 
connections including factory made connections are water tight, prior to leaving the factory the effects of transit may cause some 
connections to subsequently leak upon filling, for which 

we 

can accept no responsibility for damage or inconvenience caused. 

Once the system is full of water and devoid of air, turn on the boiler appliance and thermostats and heat both the hot water and the heating 
circuits. The recommended hot water storage temperature is 60

o

C. Adjust the auto bypass valve as per the manufacturers instructions 

included. Check all components are functioning correctly and that there are no leaks present. 

Summary of Contents for Evocyl

Page 1: ...TALLATION MANUAL ISSUE 1 2018 FOR MORE INFORMATION GO TO WWW THERMAQ CO UK IMPORTANT By installing this product you agree to be bound by the terms and conditions supplied within the manual or available for download via our website ...

Page 2: ... manual These connections include cold mains to inlet control set equalised cold supply from inlet control set hot water draw off secondary return connection where fitted expansion vessel vessel bracket and vessel fitting and tundish disharge pipework PRIMARY WATER CONNECTIONS All primary pipework connections are 22mm compression with gland nut and olive at each connection point and require connec...

Page 3: ...ease all air from the auto air valve at the highest point of the pre plumb pipework and also any other high points in the system The normal fill pressure is 1 0 bar to 1 5 bar check both the boiler and radiator manufacturers requirements During filling ensure all plumbing connections including factory made connections are water tight prior to leaving the factory the effects of transit may cause so...

Page 4: ...ff Cold Inlet Secondary Return where fitted Heating Flow Zone 2 Heating Flow Zone 1 Balanced Cold Expansion Vessel Tundish Discharge Heating Return Return To Boiler Flow From Boiler Twin Zone Cylinder Depicted For Illustration Purposes Only ...

Page 5: ...4 SINGLE ZONE WIRING REQUIREMENTS ...

Page 6: ...5 TWIN ZONE WIRING REQUIREMENTS ...

Page 7: ...tat 1 Room Stat 2 ThermaQ SMART Wi Fi Pre Plumbed Wiring Centre Links should be put into the Programmer strip from L to CH1 CH2 to ensure the Room Stat L 1 terminal is always live For any questions or for more information please contact ThermaQ on 01924 270847 SMART Wi Fi Wiring Requirements The following diagram details how to link the wiring centre to the Wi Fi SMART controls L E N L 1 N N 0 L E...

Page 8: ...ThermaQ Limited Sandbeds Trading Estate Dewsbury Road Ossett WF5 9ND Tel 01924 270847 Fax 01924 224283 Web www thermaq co uk ...

Reviews: