background image

 

 
 

19 

To be removed part 

 

 

4.4.2 Cable connection procedure 

 

 

WARNING!!! All connections of the UPS must be done by a qualified service personal. 

 

After positioning the UPS, the cables must be connected as described below: 

1. Verify all switches of the UPS in 

“0” 

position. 

 
2. Connect the AC input coming from the mains distribution panel to the input terminals in correct phase se-

quence.  

 
WARNING!!! Make sure phase order is correct. 
If  there  is  any  incorrect  connection  in  the  phase  sequence,  the  UPS  will  not  run.  In  this  case  the 
phase sequence must be corrected. 

 
If A21 ROTATE PHASE, message appears on the LCD panel, change the phase sequence. 
 
3. Connect the output of the UPS to the load distribution panel. 
  
4. Connect the battery group, refer to battery installation section.  

 
WARNING: DO NOT TURN ON THE BATTERY FUSE (F1) BEFORE STARTING THE UPS 
 

5. Connect the copper earth bus, which is under the safety earth and the cables power connection. 

 
Note:

 The earth and the neutral connections must be in accordance to the local Rules. 
 

 
 
 

4.4.3 Description of connection terminals of the UPS :

 

 
 
 
 
 
 
 
 
 
 
 
 

Figure-6 Standard connection 

  

 
 
 
 
 
 
 
 
 
 

Figure-7 Split (external) by-pass source connection 

 
 

For Split bypass,

 

a. 

Remove the connection between K2 and K3 as shown in figure 7. 

b. 

Connect the phase and neutral from by-pass source to K2 and K4 terminals. 

c. 

Connect 3 phase input power cable to U1-V1-W1 terminals. 

 
 
 

Summary of Contents for XA-200P Series

Page 1: ...XA200P SERIES UPS s XA206P XA210P XA215P XA220P XA230P 6 10 15 20 30 kVA 3 Phase Input 1 Phase Output USER MANUAL...

Page 2: ......

Page 3: ...EL OPERATION 13 3 1 Introduction 13 3 1 1 Redundancy 13 3 1 2 Power Increase 13 3 2 Parallel Operation Mode 13 3 2 1 Redundant Parallel Mode 14 3 3 Parallel Operation Mode Fault Codes 14 3 4 Parallel...

Page 4: ...ult checking and troubleshooting 24 VIII UPS s REMOTE CONTROL CONNECTION 25 8 1 Using Serial Port 25 8 2 Serial port connection cable 26 8 3 Remote control connection with a modem 26 8 3 1 Hardware Co...

Page 5: ...d in a UPS are classified as SAFETY and OPERATING categories as shown below Kg Pb H2 SO4 HIGH VOLTAGE WEIGHT ISOLATED LEAD ACID BATTERY ATTENTION FOLLOW INSTRUCTIONS BELOW READ INSTRUCTION MANUAL SAFE...

Page 6: ......

Page 7: ...re used in the UPS Before maintenance turn off the device and wait at least 3 minutes to completely discharge the capacitors Make sure batteries are dis connected Unfortunate accidents may occur there...

Page 8: ...ine is connected to the output of this switch General description of UPS parts RECTIFIER CHARGER The first conversion stage from AC to DC uses a 3 phase 6 pulse fully controlled rectifier to convert t...

Page 9: ...F Switch F3 F4 F5 Input Switch MBS Maintenance ByPass Switch RS232 SNMP Communication Select Switch optionmal RS232 Communication Socket DB9 Female Emergency Stop Switch I P F6 Output Fuse Figure 1 3...

Page 10: ...0 or 230Vac N Voltage regulation tolerance 1 Nominal output frequency 50 Hz Output frequency tolerance Line syncron 1 Output frequency tolerance Free running 0 2 Efficiency 100 Load 87 88 Load Crest f...

Page 11: ...e L2 If lamp is lit inverter supplies the load There are 4 function keys on front panel these are ENTER UP DOWN and UP and DOWN keys help moving on menus key selects options ENTER key means the select...

Page 12: ...UND ON OFF is available Used for turning on off alert sound If you press ENTER key the option will change one press ON one press OFF If the OFF option is selected sound alert is turned off but if a ne...

Page 13: ...a this menu navigation through the items is performed using up and down buttons Submenu item Function 1 LD 060 Output load percentage 2 OP CURR 011A Output current 3 OPV 220 Output voltage 4 IPV 380 3...

Page 14: ...id 5 REMOTE ENABLE By using key you can change enable and disable options Enable remote battery test shutdown and bypass functions are enabled disable these functions are disabled press ENTER for 3 se...

Page 15: ...he UPS Submenu item Function 1 Password required System adjustments ENTER EXIT Enter exit from submenu Goto first submenu item 2 2 8 ADJUST MODE submenu This menu is used to adjust time and date of th...

Page 16: ...ain EMERGENCY STOP If an external EPO switch is installed to system connected to interface board to stop all UPS parts rectifi er static bypass inverter etc is possible After pressing EPO switch all p...

Page 17: ...R Over temperature inverter or rectifier section 1 Overload for inverter 2 Over temperature 3 Fan failure or dirty air inlets 4 Bad UPS settling There is not enough ventilation area A12 OVERCURRENT In...

Page 18: ...S found in parallel system A28 PLUG IN DIG Digital connection cable plug in failure A31 DUBL UPS NUMBER Parallel UPS numbers are same change one of them A40 CANT FIND PR Parallel mode is selected but...

Page 19: ...nstall one more UPS to the system 3 2 Parallel Operation Mode NOTE Parallel control board and some accessories are not installed in a standard XA200P series UPS but parallel operation option is availa...

Page 20: ...UG IN DIG Socket unplugged A31 DUBL UPS NR The same UPS number is selected for SLAVE UPS you must assign different UPS numbers to each one in parallel systems Go to SETTINGS menu and change the UPS nu...

Page 21: ...arallel UPS Connection NOTE OUTPUT CONNECTIONS MUST BE OF EXACTLY THE SAME LENGTH CAUTION During operation do not turn off CB1 CB2 CB3 or CB4 first turn off the UPS output switch then turn off the CB1...

Page 22: ...arallel UPS operates alone in ONLINE mode XA200P series requires only a parallel control board to operate in parallel mode 3 6 Taking off the parallel devices from a UPS 1 Shift to the ON LINE mode 2...

Page 23: ...shipping carton and the UPS 2 Carefully open the carton and take the UPS out 3 Retain the carton and packing material for future use Unit package contents 1 A user manual and Guarantee certificate 2 B...

Page 24: ...t take additional precautions UPS Power kVA NOMINAL CURRENT Amperes Recommended cable cross section mm 2 Input line Full capacity recharge Bypass output At full load Battery At min battery voltage 380...

Page 25: ...ppears on the LCD panel change the phase sequence 3 Connect the output of the UPS to the load distribution panel 4 Connect the battery group refer to battery installation section WARNING DO NOT TURN O...

Page 26: ...ttery block A minimum clear ance of 20 mm should be allowed between the cell surface and any walls A clearance of minimum150 mm should be allowed between the top of the cells and the underside of the...

Page 27: ...nto 0 position 5 3 Switching into maintenance bypass mode 1 Press down button until COMMAND MENU appears then press enter Press down button until ENTER BY PASS message appears Again press enter button...

Page 28: ...LEDs and parameter measurements are normal and there is no alarm message on the indicator panel 2 Check if the device is overheated 3 Check the cooling fans rotations 4 Check if there is any change i...

Page 29: ...fore storage If the charge is not enough then charge the batteries at least for 12 hours 2 Qualified service personal should disconnect the connections 3 Batteries should be charged every six months d...

Page 30: ...be recorded regularly as mentioned previously Generally the output voltage can deviate 2 from the predefined values If values differ more than this per centage then reasons must be investigated The f...

Page 31: ...alarm CANCEL battery test Turn off UPS output voltage immediately SHUTDOWN Turn off UPS output voltage after delay WAITING SHUTDOWN Turn off UPS output voltage SHUTDOWN and turn on UPS output voltage...

Page 32: ...igured to answer incoming calls To test this call the phone number connected to the modem and hear modem s voice 8 3 2 Functioning Principle The remote operator by means of a PC and a modem device and...

Page 33: ...m the NULL modem in the hyperterminal otherwise you will get ERROR Speed configuration table Modem model Speed configuration string US ROBOTICS sportster voice AT N3 APACHE AE56SP R ATN0S37 6 BOCAMODE...

Page 34: ...3 7 7 9 2 8 4 UPS Remote monitoring panel connection Remote monitoring panel is used to monitor the UPS from 400m distance This panel is installed to con trol monitor room If the distance is less than...

Page 35: ......

Page 36: ...AGKK5594 12 2012...

Reviews: