![Tellus Power UP80J Installation Manual Download Page 5](http://html1.mh-extra.com/html/tellus-power/up80j/up80j_installation-manual_1084149005.webp)
N
N
G
G
L1
L2
L1
L3
L2
L3
208V between any 2 Legs
Meter
Breaker Panel
120V between any Leg and N
40A
Any 2 Legs
N
G
G
L2
L3
“Stinger” or “High Leg”
NOT USED!
L1
L3
L2
L1
240V between any 2 legs
120V between L1 and N
120V between L2 and N
! - 208V between L3 and N - !
Meter
Breaker Panel
40A
Never connect the station to L3. The 3rd Leg of delta is 208Volts with respect to Neutral/Earth and will trip the GMI !
L1 or L2
Only
N
G
G
L2
L1
L1
L2
L1
L2
240V between L1 and L2
120V between L1 or L2 and N
Meter
Breaker Panel
UP80J Station
40A
G
L1 & L2
240V
Level-2
L1
L2
UP80J Station
G
240V
Level-2
L1
L2
UP80J Station
G
240V
Level-2
N
N
!
Size conduit to carry five
(5) wires:
(4) 30 Amp continuous
load rated conductors,
and (1) earth ground
Size conduit to carry five
(5) wires:
(4) 30 Amp continuous
load rated conductors,
and (1) earth ground
Size conduit to carry five
(5) wires:
(4) 30 Amp continuous
load rated conductors,
and (1) earth ground
240/120V SINGLE Split Phase (preferred service)
240V 3-Phase, DELTA-Connected, one leg center tapped (difficulty balancing multiple stations)
208V 3-Phase, WYE-Connected (attention to balancing required for multiple stations)
Page 5
Service Wireing Options:
5A
5B
5C
KIT301-IM-20140501