Electrical:
Each UP80J EV s

tation offers 1 Level-2 standard coupler, therefore requiring 1 dedicated 208-24 

0VAC circuit and an earth/ground wire for a total of 3 wires running to the station. 

Input/output voltage: 208 to 240VAC
Input service breaker:  Dedicated 40 Amp double pole breaker (non-GFCI) 
Max output current: 30 A
Output connector: SAE J1772TM connector with up to 25ft cable
Standby power consumed: < 10Watts continuous
Total max. output power from station: 7.2 kW

Networking:  
LAN: Physically and digitally secure hard wired Cat 5 between master and slave stations 
WAN: Cellular data network options are available for the master station.

Safety and operational:
Safety:   ETL listed to UL2594 UL2231-1, UL2231-2, and UL991.  Meets NEC Article 625/SAE J1772
Operating temperature:  -30°F to +130°F (-35°C to +55°C )
Operating humidity: Up to 95% non-condensing
Enclosure rating: NEMA 3R
Terminal block temperature rating: 212°F (100°C)

Interface devices:
Screen: Heated full color transflective LCD display, with auto brightness adjust for ambient light
RFID reader: Active multi-standard
Touch pad:  Backlight numeric membrane type buttons
LED status indicators: RGB led with auto brightness adjust for ambient light 
                               
Safety devices:
Ground fault detection:  20mA Charge Circuit Interrupt Device (CCID20) including 3 auto retry 
(15 minute delay between each auto retry) 

Detection devices:
Level-2 plug-out detection: Power cutoff per SAE J1772TM
Power metering: 2% accuracy collected at intervals that are configured at the server. 
Local grid health: Service line voltage and frequency detection and logging.
Ambient light sensor: Automatically adjusts brightness of screen and indicator LEDs.
Ambient temperature sensor:  Controls heating of LCD display in extreme cold.

Physical Strength:
Housing wall:  1/4” thick aluminum 6061 T6 (No additional protective bollards necessary)
Base for pad mount housing (UP_PMP) unit: 12”x12”x1/2” thick aluminum 6061 T6  
End caps:  Solid aluminum T6
Interface parts: Latest UV resistant poly carbonate technology
Hardware:  All internal and external hardware is stainless steel
Vandal protection: Custom external security fasteners (stainless steel)

Available Housing Post Dimensions:
Pad Mount Post (UP_PMP):  7” cylinder with a height of 70” and base of 12”x12”x1/2” thick
Direct Burial Post (UP_DBP):  7” cylinder with a height of 102” 
Wall/Pole Mount Post (UP_WMP):  7” cylinder with a height of 54” 

Page 3

Specifications:

KIT301-IM-20140501

Summary of Contents for UP80J

Page 1: ...wer com www telluspower com UP80J Networked EV Charging Head Unit Installation Manual 20140501 The UP80J is an electric vehicle charging head designed for installation into GRIDbot standard UP housing...

Page 2: ...FY This GRIDbot station should not be modified in any way This will void the warranty compromise protection and could result in a possible shock or fire hazard OPERATING CAUTIONS Ensure that the charg...

Page 3: ...pe buttons LED status indicators RGB led with auto brightness adjust for ambient light Safety devices Ground fault detection 20mA Charge Circuit Interrupt Device CCID20 including 3 auto retry 15 minut...

Page 4: ...e needed Short driver handle for standard bits Right angle driver ratchet for standard bits Set of SAE wrenches Hole cutting drill bits to match conduit size Spirit Level Smart phone GPS coordinate co...

Page 5: ...Breaker Panel UP80J Station 40A G L1 L2 240V Level 2 L1 L2 UP80J Station G 240V Level 2 L1 L2 UP80J Station G 240V Level 2 N N Size conduit to carry five 5 wires 4 30 Amp continuous load rated conduct...

Page 6: ...h station housing then run data conduit between each Size data conduit to carry up to 2 Cat5e cables each Pull Cat5 data cable in accordance with the number of station at the site Leave 6ft of cable e...

Page 7: ...ed to the base plate by inserting it through the lock washer and into the back of the plate Thread the hardware set into base plate until it is finger tight Now tighten the locking nut down onto the b...

Page 8: ...ent Store the box in a dry place If repacking is required First place the station head the anti static bag Secure neck of bag with tie Roll cable up in to an 15 diameter coil Leave a 6 between cable c...

Page 9: ...ing and unravel the charg ing cable s Thread the level 2 coupler s downwards though the black rubber strain relief loop near the base of the station housing post Pull most of the cable s through Loose...

Page 10: ...First connect the green equipment grounding conductor to the grounding bar on the station head unit NOTE The station will not operate without a successful ground path to the service panel Insert one...

Page 11: ...5 7 8 on the modular jack at each end orange white orange green white blue blue white green brown white brown Test each segment of terminated cable with a simple battery operated Ethernet tester aprox...

Page 12: ...IDkey again to confirm the number on the screen matches the ID on the station housing Write the Station ID for each station at the site on the from provided on page 13 Then push the blue back button I...

Page 13: ...Station ID Qty L 1 Ports Qty L 2 Ports GPS 888 88888888 888 88888888 Station ID Qty L 1 Ports Qty L 2 Ports GPS 888 88888888 888 88888888 Station ID Qty L 1 Ports Qty L 2 Ports GPS 888 88888888 888 8...

Reviews: