Equipment rack installation
The rackmount kit is a collection of parts that, once installed, configures the MPI2 PRISM monitor (not included) and
extended touch display for mounting into a standard 19-inch equipment rack.
Rack cabinet cooling and clearance requirements
CAUTION.
To prevent risk of fire, adequate airflow to instrument(s) and rack adapter must be maintained. Failure to provide
adequate airflow to instrument(s) could cause an instrument to shut down.
Inadequate airflow includes placing instrument(s) and rack adapter in any small, enclosed room that lacks a ventilation system,
such as a closet. If the airflow is restricted or blocked and the instrument(s) do not shut down, the risk of fire is increased and the
instrument(s) could be permanently damaged.
The instrument has specific cooling and clearance requirements. Make sure that the clearance requirements for proper
airflow are met for both the rack cabinet and the instrument. See the
PRISM MPI2 Installation and Safety Instructions
manual
for information about the environmental operating requirements for the instrument.
Table 4: Clearance requirements for the rack cabinet
Instrument side
Clearance requirement
Top and bottom
None
Left and right sides
2 in (51 mm)
Front
None
Rear
3 in (76 mm)
Recommended tool list
Table 5: Recommended tool list
Name
Description
Screwdriver handle
Torque driver handle. Accepts 1/4-in. hex-head driver tips
#2 Phillips tips or PoziDriv tip
Phillips or PoziDriv-driver tip for #2 size screw heads
T-10 TORX tip
Used for removing instrument screws. TORX-driver bit for
T-10 size screw heads.
T-15 TORX tip
Used for removing instrument screws. TORX-driver bit for
T-10 size screw heads.