Dual-Feed 600A Load Center Frame
600CB10 & 600CB12 Installation Guide
6
© Telect, Inc. All rights reserved. 7.14.17 136429-2
509.926.6000 :: www.telect.com
3. If you intend to install alarm wiring for load center
and/or bay alarms, consider doing so now before
installing the load center in the rack. The alarm
terminal is located near the top center of the load
center. Refer to Figure 5.
a. If you intend the alarm wires to exit at the back
of the rack, don’t forget to feed alarm wiring
from the back to the front of the rack before wire
wrapping the alarm pins.
b. It is possible to use a short, manual wire-wrap
tool to install alarm wiring after securing the load
center to the rack. If you intend to use a power
or larger manual wire-wrap tool, you must install
alarm wiring now.
Figure 4 – Alarm Board Jumper Settings
Figure 5 – Alarm Wiring