BATTERY TEST MODE

>FULL TIME

 2/3 OPERATION TIME

 TO UNDERVOLTAGE

BATTERY OPERATION 

 

TIME

  090 MINUTES

7.6.1   Luminaire Test Time

Settings > Lum. test settings > Set time

•  Set the time you want the luminaire test to start at by rotating the 

selection button

•  Short press of the button moves the selection to minutes

•  Long press of the button saves the time and exits the menu. 

Note!

 Please note that the luminaires may blink during the tests. 

The test time should be set in a way, that the building is empty, 

for example outside business hours.

 

7.6.2  Time Interval for Luminaire Tests

Settings > Lum. test settings > Set interval

•  Set the time interval for luminaire tests. 

1 Day(s)

 = tests are run 

every day. 

7 Day(s)

 = tests are run every week.

7.7  Battery Settings

Settings > Battery settings

•  Set operation time

: Set the intended operation time for batteries 

(for testing purpose))

•  Battery test mode

: Battery test settings

•  Set switch delay

: Set a delay for battery mode switch

•  Battery test date

7.7.1  Battery Operating Time

Settings > Battery settings > Set operation time

•  You may choose an operation time for the batteries between 

60–240 minutes. This value is used for testing the battery.

 

7.7.2  Battery Test Mode (test time)

Settings > Battery Settings > Battery test mode

•  Full time

: Tests the battery for full user set operation time .

•  2/3 Operation time

: Tests the battery for 2/3 of user set operation 

time, and compares remaining charge to the battery capacity

•  To undervoltage

: Tests the battery until undervoltage

•  Note! The batteries must be completely charged before running 

tests. 

LUM. TEST START TIME
  09:00

  

˄˄

BATTERY SETTINGS

>SET SWITCH DELAY

 BATTERY TEST DATE

LUM. TEST INTERVAL

  1 DAY(S)

Summary of Contents for TKT24 series

Page 1: ...TKT24series Installation and User Guide Addressable 24 V Central Battery Unit...

Page 2: ...DICATOR LEDs This product may only be installed or maintained by a qualified electrician Central Battery Unit is ON Mains mode Battery mode Batteries recharging Error see Chapter 8 for details about e...

Page 3: ...e System 7 3 Installing the System 7 3 1 Connections Parts and Layout 8 4 Commissioning 11 5 Structure of the User Interface 11 6 Main View 12 7 Main Menu 12 7 1 Circuit and Luminaire Configurations 1...

Page 4: ...LTAGE 16 8 3 DEEP DISCHARGE 16 8 4 BATTERY UNDERVOLTAGE 16 8 5 TEMPERATURE ERROR 16 8 6 MAINS NOT PRESENT 16 8 7 MOSFET BROKEN circuit board number 16 8 8 LUMINAIRE BROKEN 17 8 9 FUSE ERROR 17 9 Mecha...

Page 5: ...ctions Testing of addressable luminaires and the monitoring of their operation indicaties the address of faulty luminaire Tests the batteries automatically Tests can also be started manually Self lear...

Page 6: ...4 AT Battery Fuse Circuit breaker32 A 250 VDC Output connector Max wire 4 mm Mass without batteries TKT2404C 11 1 kg TKT2408C 16 0 kg Voltage limits When mains drops below 165 VAC the CBU supplies vol...

Page 7: ...m the documents delivered with the luminaires 3 Installing the System Make sure to read Chapter 3 1 Connections Parts and Layout installing the system 1 Open the case by unfastening the two screws 2 A...

Page 8: ...n there is an internal fault in the CBU luminaire error does not change the relay position Remote control When a relay connected to this is in normal open position the CBU goes into battery mode 3 1 2...

Page 9: ...y connections Relays remote ctrl and temp sensor Output circuits Battery shelf Holes for cables For circuit cables and mains also on top Data connection RS485 Connection for ACM modem Wall mounting Wa...

Page 10: ...20 240V AC 50 60Hz 1 L N PE RS485 connection for ACM B A ERROR relay BATT relay WORK relay Temperature sensor Remote Control Output Circuits L 1 2 3 4 5 6 7 8 Output Circuits N 1 2 3 4 5 6 7 8 Circuit...

Page 11: ...rom battery mode see chapter 7 7 3 7 Optional set a password see chapter 7 7 5 8 Optional set a local address for the CBU for ACM see chapter 7 7 6 9 Get luminaire configuration see chapter 7 3 Changi...

Page 12: ...configuration Empty There is no luminaires in the circuit OK Circuit contains luminaires all functioning normally Error Circuit contains luminaires one or several luminaires have reported and error V...

Page 13: ...tings Local address Set a local address for the CBU for ACM Setup password Set a password to protect the system from unauthorized access 7 5 Setting the Time Settings Set time and date Set the time an...

Page 14: ...Battery Settings Settings Battery settings Set operation time Set the intended operation time for batteries for testing purpose Battery test mode Battery test settings Set switch delay Set a delay for...

Page 15: ...st to a national holiday 7 7 5 Password Protection Settings Setup password Set a four digit password with the selection button Save the pass word and exit by pressing the selection button long If you...

Page 16: ...lts Error will be removed after the battery voltage exceeds 19 6 volts and the user aknowledges the error message by pressing teh selection button During the error the CBU will be in power save mode 8...

Page 17: ...uminaire and replace or fix the luminaire 8 9 FUSE ERROR There are luminaires defined for a circuit but there is no electrical load in the circuit Check the circuit fuse If there is only one luminaire...

Page 18: ...18 6 500 431 62 22 477 604 112 604 477 112 22 9 Mechanical Dimensions TKT2404C...

Page 19: ...19 6 431 500 62 22 477 604 200 604 477 200 22 10 Mechanical Dimensions TKT2408C...

Page 20: ...200 Lahti Tel 358 3 883 020 Fax 358 3 883 0240 emexit teknoware com teknoware com We reserve the right to make modifications without notice 2018 Teknoware All rights reserved 11 2018 TKT24 Central Bat...

Reviews: