![TechnipFMC Smith Meter AccuLoad IV Installation & Maintenance Manual Download Page 17](http://html1.mh-extra.com/html/technipfmc/smith-meter-accuload-iv/smith-meter-accuload-iv_installation-and-maintenance-manual_1069431017.webp)
AccuLoad IV Installation & Maintenance Manual
Introduction
12
“Warning: Clean display with a damp cloth only.” This is to ensure that stray static charges are not built
up on the surface that could lead to a static discharge.
•
Special care must be taken with shielding termination to ensure signal integrity. See
Electrical Installation Requirements
for more information.
•
The AC and DC wiring should be physically separated (do not use the same conduit or entry) to avoid
induced noise.
ATEX- and IEC-approved installations have special requirements; see
To ensure the correct operation,
Section 3.6.7: Typical Wiring Diagrams
1.2.4 RF Radiation
The AccuLoad generates, uses, and can radiate radio frequency (RF) energy and, if not installed and used
in accordance with this manual, may cause interference to radio communications. It has not been tested to
comply with the limits pursuant to Federal Communications Commission’s FCC Code of Federal
Regulations, Title 47, Part 15 (CFR 47), as electronic control equipment used by an industrial complex is
exempt from the rules.
Operation of this equipment in a residential area may cause interference, in which case the user, at their
own expense, will be required to take whatever measures that may be necessary to correct the
interference. The explosion-proof version of the AccuLoad has been evaluated against international
standard IEC 61326-1: Electrical Equipment for Measurement, Control and Laboratory Use and has been
found to comply with European Community Electromagnetic Compatibility (EMC) Directive 2014/30/EU.
1.2.5 Site-Specific Configuration
The AccuLoad is shipped from the factory in a completely initialized state and must be properly configured
for the specific installation prior to operation. The unit will not operate due to alarm conditions until the
configuration is completed. Using a personal computer (PC) running the AccuMate application is the best
method to set the initial configuration, but if AccuMate is not available, all configuration parameters are
accessible using the AccuLoad’s touch screen. See the AccuLoad IV Operator Reference Manual
(
MN06200
) for information about parameter settings.
1.2.6 Weights and Measures Requirements
The AccuLoad is used by a global market. Requirements regarding weights and measures may vary
depending on the region. Users are required to verify that the AccuLoad is configured and operated in a
manner consistent with local codes and that proper notification (permit for use) or registration has been filed
with the local authority or jurisdiction.
Weights and measures authorities rely on either physical sealing or electronic sealing with password
protection to secure metrological parameters for use in legal trade. See
Section 5.2: Sealing the Enclosure
in this manual for information about physically sealing the AccuLoad or the AccuLoad IV Operator
Reference Manual (
MN06200
) for instructions on setting a password.
Summary of Contents for Smith Meter AccuLoad IV
Page 7: ...AccuLoad IV Installation Maintenance Manual Introduction 2 Figure 1 AccuLoad IV ST ...
Page 9: ...AccuLoad IV Installation Maintenance Manual Introduction 4 Figure 3 AccuLoad IV QT ...
Page 11: ...AccuLoad IV Installation Maintenance Manual Introduction 6 Figure 5 AccuLoad IV N4 ...
Page 14: ...AccuLoad IV Installation Maintenance Manual Introduction 9 Figure 8 AccuLoad IV SA FCM ...