Product Levitator-4 Produced by Tayplay Ltd
Leg Foot
x4
Levitator Leg
x4
Levitator Tie
x8
Installation instructions
The
Levitator 4
is delivered in two sections
The Reinforced Rubber Centre and Rope Net.
1.
The dismantled corner legs & ground chain/rigger with fixings for easy assembly
2.
Only section 2. is required at this point so the first piece should be left wrapped
and stored safely until the groundwork's have been completed and the concrete been
given sufficient time to cure.
Foundation requirements
General
The Levitator
Net has been designed to allow a rubber safety surface to be placed
below the net,the surface thickness should be based on the CFH of 1595mm.
It is recomended the area is prepared accordingly prior to commencing installation of
the net.
Equipment & Tools
The following equipment is recommended to assist in the accurate installation of the
foundation feet.
1) Laser Level 2) 20m Measuring Tape 3) JCB Excavator 4) Set Timber
5) Manual Tools: Spade, Sledge Hammer, Claw Hammer & Nails
6) A252 Steel Reinforcement Mesh
It is recomended that you have a mininum of three people to lift and assemble the
Levitator.
Time Management
Day One:
1) Set out the Area 2) Accurately Position and Excavate Holes
3) Secure for concreting 4) Press Reinforcement Mesh Into the top of fresh concrete.
Day Two:
1) Concrete Foundations
Day Three*:
1) Set out Levitator Feet Positions. 2) Bolt feet into concrete foundations.
3) Laying of rubber safety surface material
Day Four:
1) Assemble Leg Assemblies 2) Insert keys in legs and loosely attach rigging screws.
3) Attach the Rubber Membrane to the disc end fittings on the net.
4) Go around tensioning the rigging screws until rubber lies flat.
*The foundation should be left for approximately seven days to achieve maximum
strength prior to assembling the remaining elements.
Infill Panel
x4
A252 Steel Mesh Reinforcement
Not Supplied
Leg Bracket
x4
Rigger/Chain
x4
Product
Levitator-4
Page Three