background image

Product Levitator-4 Produced by Tayplay Ltd

Leg Foot

x4

Levitator Leg

x4

Levitator Tie

x8

Installation instructions

The 

Levitator 4

 is delivered in two sections

The Reinforced Rubber Centre and Rope Net.

1.

The dismantled corner legs & ground chain/rigger with fixings for easy assembly 

2.

Only section 2. is required at this point so the first piece should be left wrapped 

and stored safely until the groundwork's have been completed and the concrete been 

given sufficient time to cure.

Foundation requirements

General

The Levitator

 

Net has been designed to allow a rubber safety surface to be placed 

below the net,the surface thickness should be based on the CFH of 1595mm.  
It is recomended the area is prepared accordingly prior to commencing installation of 

the net.

Equipment & Tools

The following equipment is recommended to assist in the accurate installation of the

foundation feet.
1) Laser Level 2) 20m Measuring Tape 3) JCB Excavator 4) Set Timber

5) Manual Tools: Spade, Sledge Hammer, Claw Hammer & Nails

6) A252 Steel Reinforcement Mesh
It is recomended that you have a mininum of three people to lift and assemble the 

Levitator.

Time Management

Day One:

1) Set out the Area 2) Accurately Position and Excavate Holes

3) Secure for concreting 4) Press Reinforcement Mesh Into the top of fresh concrete. 
Day Two:

1) Concrete Foundations
Day Three*:

1) Set out Levitator Feet Positions. 2) Bolt feet into concrete foundations.

3) Laying of rubber safety surface material
Day Four:

1) Assemble Leg Assemblies 2) Insert keys in legs and loosely attach rigging screws.

3) Attach the Rubber Membrane to the disc end fittings on the net.

4) Go around tensioning the rigging screws until rubber lies flat.

*The foundation should be left for approximately seven days to achieve maximum

strength prior to assembling the remaining elements.

Infill Panel

x4

A252 Steel Mesh Reinforcement

Not Supplied

Leg Bracket

x4

Rigger/Chain

x4

Product

Levitator-4

Page Three

Summary of Contents for Levitator 4

Page 1: ...e used by children from 3 years of age and has been manufactured to exceed the European playground standards EN1176 1 2008 and EN1176 11 2014 The following installation instructions should be adhered...

Page 2: ...bber safety surface as shown above is needed See table below for recomended Surface Types and Depths Space requirements Safety Clearances The requirements for space and safety clearances are extracted...

Page 3: ...f the foundation feet 1 Laser Level 2 20m Measuring Tape 3 JCB Excavator 4 Set Timber 5 Manual Tools Spade Sledge Hammer Claw Hammer Nails 6 A252 Steel Reinforcement Mesh It is recomended that you hav...

Page 4: ...tion position Excavation Foundation Positioning Procedure In loose ground it may be necessary to use timber framework or shuttering to prevent soil falling into the hole It will also prevent an unnece...

Page 5: ...d layout the feet using the measurements above These will position around the already place ground chain points Bore 10mm holes 130mm deep for the feet to be bolted directly ontop of the concrete surf...

Page 6: ...w unwrap the rubber membrane and net assembly and lie in the correct orientation The rope netting and reinforced rubber membrane need to be unattached before connecting the net to the legs Work your w...

Page 7: ...n your net is wound up The net will need to be tensioned by fully winding up the rigging screws at a later date See maintenance for more Product Levitator 4 Produced by Tayplay Ltd Reinforced Rubber M...

Page 8: ...e inspection of the following as a minimum General equipment and surface cleanliness 1 Equipment ground clearances are maintained 2 Foundations not exposed loose in the ground or cracked 3 Parts not m...

Reviews: