ELECTRICAL CONNECTION
The electrical contractor must follow the electrical specification
supplied with the ABS
42
00 system
Ensure all electrical works are only completed by licenced persons.
Ensure all electrical work is completed and compliant with AS/ANZ 3000.
Refer to Electrical Specifications on Page 12 & 13
9.
COMMISSIONING
Please ensure the following is completed prior to having the system commissioned
Tanks is full of water (5,000lt each)
Effluent Disposal area is installed
Effluent Disposal Area feed line is connected to ABS
42
00 (Tank 2)
Electrical power is connected (Tank 1 & 2)
Drains connected (main sewer into tank 1 and connection between Tank 1 & 2)
IMPORTANT: The Taylex
ABS
42
00 System cannot be commissioned unless power is
connected to the system.
The ABS
42
00 will then be switched on (commissioned) by an Employee of Taylex
Australia
,
a Taylex
Accredited Distributor (TAD) or a Taylex
Accredited Service Technician (TASA).