TAYLEX ABS 

EXCAVATION INSTRUCTIONS

ABS CONCRETE STANDARD 

Excavation Instructions

Tank Total Mass = 6.25 Tonne

2300 mm

1530 mm

670 mm

3000 mm

2425 mm

100 mm

2300 mm

100 mm

350 mm

32mm 

Irrigation

Outlet

Lifting 

Hole

20mm

Electrical

Inlet

100mm 

Inlet

Lifting 

Hole

Lifting 

Holes

100mm 

Inlet

Lifting 

Holes

100mm of  

5mm-7mm 

drainage

gravel or sand

Please Note:

5,000lt of water 

to be placed in 

this chamber to 

prevent flotation

Lifting 

Hole

1. Dig hole 3000mm square & 2300mm

Deep

2. Ensure drainage has a 1/60 fall to the

inlet of ABS. Risers are available if the

tank needs to be installed deeper in the

ground to maintain fall

3. Cover base of hole with 100mm of

5mm to 7mm drainage gravel or sand

4. Ensure bottom of hole is level

5. Backfill with soil from Excavation in no

more than 500mm equally distributed

layers around the tank. Avoid backfilling

with rocks over 300mm.

6. To prevent flotation, fill the ABS with

5,000lt of water immediately through

hole above the aeration chamber

(see diagram below)

7. Ensure top of gravel/sand is 1530mm

to bottom of inlet

ELECTRICIAN

Connect through conduit on side of ABS. 
Run wire (min 2.5mm) through the flexible 
conduit provided and up into the switch located 
in the blower box.
Active - Neutral - Earth. 

TRUCK ACCESS

Unloading of ABS via the back of the truck
NOT SIDE. Ensure BACK of truck has clear 
level 6m wide access to the edge of the hole.

REACH OF CRANE/ CRANE TRUCK

To be determined by your crane/ crane truck
operator.

Top of tank to be a minimum

of 100mm above landscaped ground level

Page 

8

 of 1

5

 

Summary of Contents for ABS

Page 1: ...INSTALLATION MANUAL CONCRETE ADVANCED BLOWER SYSTEM ABS ABSNR...

Page 2: ...ABS Standard Lifting Instructions 9 c ABS Tall 400 Excavation Instructions 10 d ABS Tall 400 Lifting Instructions 11 e ABS Tall 600 Excavation Instructions 12 f ABS Tall 600 Lifting Instructions 13 1...

Page 3: ...EN WET During cleaning maintenance repair work the surrounding area may become extremely slippery due to spilt water Caution is to be taken when walking standing near the ABS when these activities are...

Page 4: ...oil moisture for heavy equipment access Weather conditions 5 MARK OUT To ensure the ABS is installed in the position nominated by the Home Owner Builder the location of the ABS should be marked out pr...

Page 5: ...n behind the vehicle before placing it into the prepared hole Maximum reach from the rear of the truck to the centre of ABS will vary depending on the size of the crane To enable the ABS to be unloade...

Page 6: ...Page 5 of 15...

Page 7: ...cess is the responsibility of the property owner builder 7 INSTALLATION Always ensure the installation location include the future landscaping provision allow for the diversion of stormwater and surfa...

Page 8: ...ibuted layers around the tank perimeter Ensure that sand or excavated material does not fall on the lid of the ABS as this will fall into the system through the manholes and clog the system and irriga...

Page 9: ...mm drainage gravel or sand 4 Ensure bottom of hole is level 5 Back ll with soil from Excavation in no more than 500mm equally distributed layers around the tank Avoid back lling with rocks over 300mm...

Page 10: ...hrough TOP lifting holes provided in the lid of the ABS 3 Loop chains through the lifting holes directly below on the inside wall of the ABS 4 Steel reinforcing bars have been installed inside the con...

Page 11: ...distributed layers around the tank Ensure there is no backfilling with rocks over 300mm 6 To prevent flotation fill the ABS with 5 000lt of water immediately through hole above the aeration chamber s...

Page 12: ...p and blower to the double GPO s Turn all 3 GPO Switches ON Taylex Electrical Connection Diagram TITLE DATE Taylex ABS ABSNR 01 01 2023 TAYLEX ABS ABNSNR ELECTRICAL CONNECTION DIAGRAM Electrician Conn...