You should have:
• 1 Radiator
• 4 Bracket Closing Caps
• 4 Bracket Hooks
• 4 Bracket Back Plates
• 4 Bracket Screws
You will need:
• Tape measure
• Electric drill and bits
• Spirit level
• Airvent key
• Appropriate wall fixings
• Spanner for valves and
vents
2. Contents
Technical Specifications
Materials
Aluminium
Connections
½" flow and return.
Test pressure
9 Bar
Testing authority
EN442
Maximum operating pressure
6 Bar
Maximum working temperature
90 ºC
Packaging
Polystyrene protection in cardboard box
All products must be inspected once removed
from the packaging and your point of purchase
notified within 28 days of delivery of any
scratches, blemishes or other damage. Your
point of purchase will then agree appropriate
action.
Imperfect radiators should therefore not be
fitted and we will not accept responsibility for
replacement of scratched or damaged radiators
once they have been fitted. This includes any
consequential loss or cost of fitting.
If we are not notified within 28 days of the
date on the signed delivery note then it will be
deemed that we have fully complied with our
obligations and claims will not be considered.
Failure to comply with any of the above may
invalidate any claims. We recommend that
after you check the product on delivery that it is
stored in its packaging to prevent damage prior
to installation, we cannot accept responsibility
for items damaged after delivery.
For full details of our Terms and Conditions
please visit www.supplies4heat.co.uk or call us
on 01342 306880.
Terms & Conditions
This product is guaranteed for 10 years. As we are not the manufacturers of this product
we will take all reasonable endeavours to make over to you the benefit of any warranty
or guarantee given by the manufacturer.
The guarantees in all cases are subject to the products being installed in accordance with
British and or European standards as well as these fitting instructions. The guarantees in
all cases are restricted to the free of charge replacement or repair of the failed product
only. Our liability will under no circumstances extend beyond the repair or replacement
of the product supplied by us. Claims for either labour in replacement or damage to
property are not admissible. Any goods that are returned, in the event of a problem,
will belong to us.
Guarantees & Liabilities
www.supplies4heat.co.uk 01342 306880
Refer to diagrams overleaf when installing
1. Accurately mark bracket holes on the wall using a tape measure
and spirit level. The bracket centres are positioned 153mm down
from the top collector, and 103mm from either side.
(Height of the radiator from floor : minimum 100mm)
2. Using suitable drill bits and plugs, insert suitable wall plugs. To
hang the top two brackets, secure the backplate ‘A’ with screws ‘B’
(or other suitable screws) going through into the wall plugs.
3. Insert the bracktets ‘C’ down into the back plate ‘A’ and secure
with the provided screw ‘D’. Then fit the closing cap ‘E’ on top.
3. Installing radiator
Please Note: In accordance with Part L1 2006 of
the Building Regulations and BS7593:1992 code of
practice for the treatment of hot water and central
heating systems, we strongly recommend flushing
the heating system post installation of new radiators
and then adding the correct quantity and type of
inhibitor for use with your radiator and system to
prevent corrosion. Damage caused to systems not
protected by a suitable inhibitor will not be covered
by manufacturer’s guarantee.
5. Commission Radiator
Please Note:
the diverter is marked with a yellow
cap and is fitted on the radiator. The diverter can
be removed and swapped to the other side if
required. However, we will not be liable for any
damages to the radiator or paint finish as a result
of moving the diverter.
4. Hang the radiator on the
second space
5. With the brackets in the correct position,
take down the radiator and fit the bottom
two brackets by repeating steps 1 to 4.
E
D
C
A
PLEASE NOTE:
To reduce the possibility of noise caused by rapid heating and cooling
of aluminium radiators; adequate capacity for expansion must be provided within
the overall heating system. Systems using micro bore pipework must have adequate
pressure and flow rates for the number and style of radiators on the system.