Chapter 2 Installation and wiring
5
Chapter 2 Installation and wiring
This chapter describes the detailed methods of installation and wiring of the
instrument, which is mandatory for technician to learn when using the instrument
for the first time.
Upon arrival of the instrument, operation procedures from unpacking,
installation, wiring to the normal operation are as shown in Figure 2-1.
Unpacking
configuration
put in operation
wiring
power supply
Installation
Fig. 2-1 Flowchart from unpacking to putting in operation
2.1 Unpacking
Upon receiving the instrument, first of all, check if the package is intact. Do
not apply excessive force to the box when unpacking. The box should face
upward. Open it from the seal, and carefully remove the instrument from the box.
Make sure the shell is not deformed, damaged or broken. You can check the
equipment and other items according to the packing list.
2.2 Installation
Instrument operating environment will not only affect the normal use of the