SC847BE1C/2C Chassis Manual
5-8
Figure 5-6: Installing into a Rack
Standard Chassis Installation
Installing the Chassis into a Rack
1.
Conirm that the inner rails are properly installed on the chassis.
2.
Conirm that the outer rails are correctly installed on the rack.
3. Pull the middle rail out from the front of the outer rail and make sure that the
ball-bearing shuttle is at the front locking position of the middle rail.
4. Align the chassis inner rails with the front of the middle rails.
5. Slide the inner rails on the chassis into the middle rails, keeping the pressure
even on both sides, until the locking tab of the inner rail clicks into the front of
the middle rail, locking the chassis into the fully extended position.
6. Depress the locking tabs of both sides at the same time and push the chassis
all the way into the rear of the rack.
7. If necessary for security purposes, use screws to secure the chassis handles
to the front of the rack.
Ball-Bearing
Shuttle
Stability hazard. The rack stabilizing mechanism must be in place, or the
rack must be bolted to the loor before you slide the unit out for servicing.
Failure to stabilize the rack can cause the rack to tip over.
Warning: When initially installing the server into a rack, test that the rail
locking tabs engage to prevent the server from being overextended. Have
a rack lift in place as a precaution in case the test fails.
Note: igures are for illustrative purposes only. Always install servers into racks
from the bottom up.
Summary of Contents for SC847BE1C series
Page 12: ...SC847BE1C 2C Chassis Manual 1 4 Notes...
Page 57: ...4 19 Chapter 4 Chassis Setup and Maintenance Figure 4 22 Placing the System Fan...
Page 60: ...SC847BE1C 2C Chassis Manual 4 22 Notes...
Page 70: ...SC847BE1C 2C Chassis Manual 5 10 Notes...
Page 76: ...SC847BE1C 2C Chassis Manual B 2 Notes...
Page 102: ...D 8 SC847BE1C 2C Chassis Manual Notes...