4.4 Monitoring Device Installation

Sunways  STT  6~25kW  series  three  phase  inverter  supports  WiFi,  GPRS  and  RS485 
communication, you can choose according to your specific needs. 
Plug the WiFi or GPRS module into the COM port in the bottom of inverter by following the 
direction the side with indicator is up (as shown in Figure 4-19). A slight “click” sound during 
the installation represents that the assembly is in place.

22

23

4.5 System Layout of Units Without Integrated DC Switch

Local standards or codes may require that PV systems are fitted with an external DC switch on 
the DC side. The DC switch must be able to safely disconnect the open-circuit voltage of the PV 
array plus a safety reserve of 20%.Install a DC switch to each PV string to isolate the DC side of 
the inverter. We recommend the following electrical connection:

1.The GPRS version module does not need to be configured. 

2.The WiFi version module needs to be configured to the router for 

the first installation, and if the router name or password changed, 

you need to configure it again. For details, please refer to the [QUICK 

INSTALLATION GUIDE] which attached in the accessory bag.

Don't touch the waterproof plug in the card slot unless replace the 

SIM card. If the SIM card needs to be replaced, please make sure the 

card slot iscompletely sealed by waterproof plug after replacing. Any 

damages caused by the waterproof plug sealing problem will be invalid 

of warranty.

Attention

Note

Figure 4-18

Summary of Contents for STT-10KTL

Page 1: ...Grid connected PV Inverter Three Phase Dual MPPT STT 6K 8K 10K 12K 15K 17K 20K 25KTL User Manual Ningbo Sunways Technologies Co Ltd...

Page 2: ...3 3 Display Interface 12 3 4 Packing List 13 4 Product Installation 13 4 1 Selection of Installation Location 13 4 2 Mounting the Inverter 15 4 3 Electrical Connection 17 4 4 Monitoring Device Instal...

Page 3: ...rid connected inverter for power generation needs the permission of the local power supply authority 2 1 7 During the operation of the inverter the surface temperature may be higher and there is a ris...

Page 4: ...g needs to be properly grounded Danger Warning Caution Used to warn of urgent dangerous situations if not avoided it could result in death or serious personal injury Description Symbol Used to warn of...

Page 5: ...8 models which are listed below STT 6KTL STT 8KTL STT 10KTL STT 12KTL STT 15KTL STT 17KTL STT 20KTL STT 25KTL 3 1 3 Applicable grid type The applicable grid types for the Sunways STT 6 25kW series ar...

Page 6: ...r side view as shown in Figure 3 3 10 Figure 3 4 Bottom view Figure 3 5 Inverter back view 3 2 3 Inverter bottom view as shown in Figure 3 4 3 2 4 Inverter back view as shown in Figure 3 5 11 410mm 17...

Page 7: ...complete at the first time when receiving the goods See Figure 3 7 for the packing list 4 Product Installation 4 1 Selection of Installation Location The Sunways STT 6 25kW series is designed with IP6...

Page 8: ...ter Warning 14 4 2 Mounting the Inverter 4 2 1 Wall bracket installation Dimensions of wall bracket see Figure 4 4 1 Use the wall bracket as the template to mark the position of 5 holes on the wall Se...

Page 9: ...tage of each PV string does not exceed 1100V 4 3 1 2 DC connector assembly procedures 2 Peel off the DC cable insulation sleeve for 7 mm as shown in Figure 4 8 Cable type Conductor transverse area mm...

Page 10: ...se a multimeter to measure the voltage of the DC input string verify the polarity of the DC input cable and ensure that each string voltage is within 1000V Warning Open end Wrench 18 Figure 4 12 Figur...

Page 11: ...sing Otherwise it may cause electric shock Good grounding is good for resisting surge voltage shock and improving EMI performance Inverters must be well grounded For a system with only one inverter ju...

Page 12: ...fely disconnect the open circuit voltage of the PV array plus a safety reserve of 20 Install a DC switch to each PV string to isolate the DC side of the inverter We recommend the following electrical...

Page 13: ...energized before operating 3 Disconnect the AC and DC cables 24 6 General Operation 6 1 Display Operation When the inverter is turned on the following interfaces will be displayed on the OLED display...

Page 14: ...liably before shipment When a fault occurs the corresponding fault messages will display on the OLED display and in this case the inverter might stop feeding into grid The fault messages and their cor...

Page 15: ...ata Dimensions mm 550W 410H 175D Weight KG 22 25 ProtectionDegree IP65 Self consumptionatNight W 1 Topology Transformerless OperatingTemperatureRange C 30 60 RelativeHumidity 0 100 OperatingAltitude m...

Reviews: