Commissioning
After setting the country parameter, set other parameters according to the specific
requirements of the local grid. Check thoroughly if the parameters meet the
requirements before commissioning.
7.1
Inspection before Commissioning
Check the following items before starting up the inverter:
1.
The inverter is firmly secured and the site is accessible for operation,
maintenance and service.
2.
The room for ventilation is provided and nothing is left on top of the inverter.
3.
Inverter and accessories are correctly connected. Cables are routed in a safe
place and protected against mechanical damage.
4.
The specification of the AC circuit breaker is reasonable.
5.
The terminals that are unused underneath the inverter are sealed.
6.
Warning signs and labels are suitably affixed and durable.
7.2
Commissioning Procedure
Make sure all the above mentioned items meet the requirements.
1.
Turn on the external AC circuit breaker.
2.
(
Optional
) Rotate the DC switch to “
ON
”.
3.
If there is sufficient sunlight, the inverter will enter the running state and
start to feed AC power to the grid.
4.
Observe the status of the LED indicator.