After hoisting and positioning the inverter, before putting the inverter into operation, be
sure to remove the wooden blocks on the top of the inverter to avoid affecting the air
intake.
5.2.3 Fastening of Connectors
Use slings with hooks or U-hooks to hoist the inverter.
The lifting devices should be correctly connected to the inverter.
L
Liiffttiin
ng
g d
de
evviic
ce
e
H
Ho
oo
okk
U
U--h
ho
oo
okk
Connections
Notice
Insert the hook from inside
to outside.
Lateral pin of the U-hook
should be tightened.
National and local safety rules should be observed at all times.
Violating relevant safety rules may void pertinent warranty claims from
Sungrow.
5.3
Foundation
5.3.1 Selection of Installation Site
When selecting the installation site, consider the following requirements at least:
•
The installation location should be as far away as possible from chemical plants and
salt-affected areas. If it cannot be avoided, the later inspection and maintenance
cycle should be shortened.
•
Ambient and geological conditions, such as stress wave emissions, the level of
underground water table, etc.should be taken into account.
•
The ambient environment should be dry, well ventilated, and far away from
inflammable materials.
•
The ground at the installation site must be compacted enough. Relative compaction
of the ground should be equal to or greater than 98%. Otherwise, take proper
measures to strengthen the ground.