Figure 1. Showing the adhesive on the wire conduit
being installed on one side of the standing seam.
Figure 2. Shows the adhesive on the back of the
PowerFit20 module.
Figure 3. Shows the first PF20 modules installed
adjacent to the WMS wire conduit.
Align the first module near the ridge of the roof.
Ensure the module is aligned to the side of the
standing seam where the WMS wire conduit was
installed. The side of the module where there are
no junction boxes should be aligned with the top
of the WMS wire conduit near the ridge. Proceed
to peel the adhesive backing off the module and
apply pressure to the module to adhere it to the
flat space. Use a rubber wheeled roller to ensure
the proper pressure is applied to the module.
Module Installation
After the roof has been cleaned to the
requirements above, the components can be
adhered to the roof. Align one of the WMS wire
conduits to one side of the standing seam. Ensure
the side that opens is facing away from the seam.
Remove the adhesive lining and install the WMS
wire conduit with the top edge going as close
to the ridge cap as possible. This will be used to
gauge where the first module will be installed as
well as be a location to run the wiring.
With the first module adhered, use one of the
WMS spacer tubes and remove the adhesive
covering from the bottom. Center the spacer
tube and adhere it adjacent to the first module
installed on the seam. Apply pressure for the