![Sun Microsystems SPARCcenter 2000 Installation Manual Download Page 37](http://html1.mh-extra.com/html/sun-microsystems/sparccenter-2000/sparccenter-2000_installation-manual_1392453037.webp)
Cabling the System
3-3
3
Figure 3-3
Rear Screen
Note – If the room does not have a raised floor, skip steps 6 and 7. In this case,
it is not necessary to route this cable behind the kick panel.
6. Take off the kick panel by loosening the two captive screws.
See Figure 3-4. Set the panel aside.
7. Route the AC power cord and external interface cables along the bottom
panel of the cabinet and over the edge of the bottom panel.
See Figure 3-4. The cables should be between the bottom panel and the kick
panel when you replace the kick panel.
8. Connect and route any remaining interface cables.
9. Uncoil the AC power cord and plug it into a grounded wall outlet.
The outlet must be a 200-240 Vac 30-ampere circuit, dedicated solely to the
server cabinet, as described in the site preparation instructions in Chapter 1.
Warning – Risk of Electric Shock. Do NOT turn on AC power to the unit yet.
Summary of Contents for SPARCcenter 2000
Page 8: ...viii SPARCcenter 2000 2000E Installation Manual June 1996 ...
Page 14: ...xiv SPARCcenter 2000 2000E Installation Manual June 1996 ...
Page 28: ...1 14 SPARCcenter 2000 2000E Installation Manual June 1996 1 ...
Page 54: ...Index 4 SPARCcenter 2000 2000E Installation Manual June 1996 ...
Page 56: ...SPARCcenter 2000 2000E Installation Manual June 1996 ...