Installation and Operating Instructions
10002 Channel Series
10002_Channel_Series_EN_20201208_V01.docx
6
Torque settings
Torque settings (Nm)
10K grinder
Thread
8.8 ZP
18-8 SST
Cutter stack locking nuts
M6
12
8.7
M8
30
21.2
M10
55
42
1 in.
170
30K, 40K, CMD, CDD grinder
1/4 in.
8.5
5/16 in.
14.9
3/8 in.
26.7
1/2 in.
58
9/16 in.
75.9
5/8 in.
124.7
1-1/2 in.
224
Safety recommendations
In common with other items of process plant a grinder must be installed correctly to ensure
satisfactory and safe operation (refer to the Installation section). The grinder must also be
maintained to a suitable standard (refer to the Maintenance section). Following these
recommendations will ensure that the safety of personnel and satisfactory operation of the grinder is
achieved.
When handling harmful or objectional materials, adequate ventilation must be provided in order to
disperse dangerous concentrations of vapours. It is recommended that where possible, Sulzer
grinders should be installed with provision for adequate lighting, thus ensure that effective
maintenance can be carried out in satisfactory conditions. With certain product materials, a hosing
down facility with adequate draining will simplify maintenance and prolong the life of grinder
components.
Noise levels
The sound pressure level will not exceed 70 dB at one metre distance from the grinder. This is
based on a typical installation and does not necessarily include noise from other sources or any
contribution from building reverberation.
Lubrication
At 10,000 hr intervals, bearings, gears and seal assembly inspection should take place along with
gear grease replenishment.