Operators Manual #513852 Rev.2
5
CBD Model Machines
A.
Move the Run switch to Program (P). A “1” is
shown on the display to the right of the minute
value and signifi es the start of a defrost mode.
B.
Press the 1...7 button to select the day of the
week. Individual days or a block of days can
be programmed. Press the 1...7 button to cycle
through all the options.
C.
Press the h and m button to set the time.
D.
Press the P button to save the setting.
E.
The display shows a “2”, which signifi es when
the machine returns to normal operation. Follow
steps B,C and D above to program the off time.
F.
Repeat programming the defrost and normal
operation start times as necessary (make sure to
program modes in pairs; every defrost start time
must have a normal operation start time).
G.
Move the Run switch to the Run position.
H.
Make sure the Auto switch is in the Auto position.
The machine operates using the programmed
defrost schedule.