Mounting instructions for springrider „frondis1“ 

Item No. 51 3012 401

State: 29.05.2020  p. 2

Play level

Foundation anchor

1.  Select the location of the play equipment taking into account the required 

minimum space (see diagram 3). 

2.  The impact area of a playground equipment with an enforced movement is 

not allowed to overlap the impact area of other equipment. 

According to DIN EN 1176-1, 4.2.8.5.2 shock-absorbing floors must be made 

on the entire impact area of every equipment that cause forced movement.

3.  Carry out excavation work for the foundation as shown in diagram 2. After 

excavation compress the foundation floor.

 

Note: 

The springrider is installed at play level. 

4.  Place the play equipment with foundation anchor as shown in diagram 2 in 

the foundation hole.

5.  Place the play equipment with foundation anchor into the concrete mass as 

shown in diagram 2, so that the base plate is surrounded by a concrete thick-
ness of at least 50 mm both above and below. 

6. 

Pour the foundation floor with concrete to a height of appr. 100 mm. 

550

100

600

480

593

 450 

OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE 

TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER 

ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER- 

WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.

1

 

Frondis1

Benennung

Gepr.

Blatt

Datum

Projekt

Gez.

Zeichnungsnummer

1:10

A3

Name

Name

Fundamentplan

0111-00-00

Maßstab

Mattheis

04.01.17

 

 

Gewerbegebiet Larsheck

56271 Kleinmaischeid

Deutschland

Beton

concrete

gewachsenes Erdreich

natural ground

Legende

stoßdämpfender Boden

shock-absorbing floor

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
SI

11.05.20

stoßdämpfender Boden

A

Datum

Änderung

Rev

550

100

600

480

593

 450 

OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE 

TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER 

ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER- 

WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.

1

 

Frondis1

Benennung

Gepr.

Blatt

Datum

Projekt

Gez.

Zeichnungsnummer

1:10

A3

Name

Name

Fundamentplan

0111-00-00

Maßstab

Mattheis

04.01.17

 

 

Gewerbegebiet Larsheck

56271 Kleinmaischeid

Deutschland

Beton

concrete

gewachsenes Erdreich

natural ground

Legende

stoßdämpfender Boden

shock-absorbing floor

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
SI

11.05.20

stoßdämpfender Boden

A

Datum

Änderung

Rev

Diagram 2: Foundation plan

Foundation

Reinforcement plan: 

Concrete foundation with reinforcement

Main foundation: BSt 500S 
Stirrups Ø 8 mm lengthwise and cross 
Concrete cover h´= 3 cm
Concrete quality class C20/25