iNSTallaTiON
installation
6
| DCE-C Trend
www.stiebel-eltron.com
Note
f
f
Install the appliance flush to the wall. The wall must
have sufficient load bearing capacity.
8.2 Minimum clearances
≥50
≥50
≥50
≥100
D
00000
79
44
2
f
f
Maintain the minimum clearances to ensure trouble-free op-
eration of the appliance and facilitate maintenance work.
8.3 Water installation
!
Material losses
Carry out all water connection and installation work in
accordance with regulations.
f
f
Flush the water line thoroughly.
Taps
Use appropriate pressure taps. Open vented taps are not per-
missible.
Permissible water line materials
- Cold water inlet line:
Pipes made from galvanised steel, stainless steel, copper or
plastic
- DHW outlet line:
Pipes made from stainless steel, copper or plastic
!
Material losses
If plastic pipework systems are used, take into account
the maximum inlet temperature and the maximum per-
missible pressure.
Flow rate
f
f
Ensure that the flow rate for switching on the appliance is
achieved.
f
f
If the required flow rate is not achieved when the draw-off
valve is fully open, remove the flow limiter from the cold
water inlet.
If required, the pressure in the water installation can also be
raised.
9. Installation
factory settings
DCE-C 6/8
Trend
DCE-C 10/12
Trend
Connected load in kW
@ 220 V
8.0
12.0
@ 230 V
8.7
13.1
Standard installation
DCE-C 6/8
Trend
DCE-C 10/12
Trend
Electrical connection from below, installa-
tion on finished walls
x
x
Water connection, installation on finished
walls
x
x
For further installation options, see chapter "Alternative instal-
lation methods".
9.1 Standard installation on finished walls
Opening the appliance
D
00000
73
64
1
f
f
Open the appliance by undoing the screw and lifting up the
appliance cover.
Preparing the power cable
B
A
D
00000
77
17
9
f
f
Prepare the power cable.
position on finished walls
Dimension a
Dimension B
Bottom, centre
30
120
Bottom, left side of appliance
20
90
Bottom, right side of appliance
20
90
Top, right side of appliance
20
80
position on unfinished walls
Dimension a
Dimension B
Bottom
20
90
Top
20
80
Summary of Contents for DCE-C 10/12 Trend
Page 59: ...www stiebel eltron com DCE C Trend 59 1 1 1 1 1 1 f f 1 1 2 1 1 3...
Page 60: ...60 DCE C Trend www stiebel eltron com 1 2 f f f f 1 3 2 2 1 2 2 70 C 43 C 3 2 3 3 55 C...
Page 69: ...www stiebel eltron com DCE C Trend 69 14 LED LED 15 f f f f f f f f...
Page 73: ...www stiebel eltron com DCE C Trend 73...
Page 75: ...www stiebel eltron com DCE C Trend 75 1 1 1 1 1 1 f f 1 1 2 1 1 3...
Page 76: ...76 DCE C Trend www stiebel eltron com 1 2 f f f f 1 3 2 2 1 2 2 70 C 43 C 3 2 3 3 55 C...
Page 85: ...www stiebel eltron com DCE C Trend 85 14 LED 15 f f f f f f f f...
Page 89: ...www stiebel eltron com DCE C Trend 89...
Page 90: ...15 DCE C Trend www stiebel eltron com...
Page 102: ...3 DCE C Trend www stiebel eltron com 1 1 1 1 1 1 e 1 1 2 1 1 3 1 2 e e 1 3 2 2 1 2 2 70 43...