Set-up and starting
31.10.2002 \\Docuserver\ba\Master\Ba_eng\UM\044_60\UM_A+S\Inbetr.fm
11
VCM 44
4.
Set-up and starting
4.1
Rotational direction check
The direction of rotation check has already been carried out during test running before the de-
livery of the VCM 44. Should, on new installation, a drive have a direction of rotation different
to that given in the table below, the polarity of the phase supply must be reversed.
The motor connections are only to be altered if, after the replacement of a motor, gear or pump,
the direction of rotation requires correction according to the following table.
To check rotational direction, disconnect the working insert from the main motor shaft, close
and lock the lid. Only start individual drives for a short time. In the following table, rotational
direction is always with respect to the view from above the machine.
4.2
Function testing and test run
The basic functions of the VCM 44 have been factory tested. In order to ensure, however, that
no damage has arisen during transport or installation, a test run of the machine should be car-
ried out shortly after its setting-up.
What to do first..
...and then carry out and double check!
Due to its own weight and low-vibration operation, the
multi-purpose machine may be installed without addi-
tional fastening.
However, it requires a firm surface to stand on.
Before starting up, you should check that the supply
voltage conforms to the operating voltage specified on
the VCM 44 rating plate. The stipulated fuse protection
must be provided.
All electrical work is only to be carried out by a
qualified electrician.
Remove all loose parts from the machine.
Loose parts flying about in the machine may dam-
age the working inserts and the motor shaft.
All electrical work is only to be carried out by a qualified electrician.
Drive
Where to test?
Direction of rotation
Arrow towards
Main motor
Spin plate beneath the bowl floor
Towards the right
End shield