Commissioning
Before commissioning, ensure the following:
• Check the mounting and installation.
• Inspect enclosure for damage.
• If necessary, remove foreign objects.
• If necessary, clean the connection chamber.
• Check whether all screws and nuts have been tightened firmly.
• Check the tightening torques.
9
Operation
The switch is driven via an axis, thus actuating the contacts.
10
Maintenance and Repair
10.1 Maintenance
• Consult the relevant national regulations to determine the type and extent of
inspections.
• Adapt inspection intervals to the operating conditions.
If core end sleeves are used, they must be attached using a suitable tool.
WARNING
Check the device before commissioning!
Explosion protection is impaired!
• Observe the inspection requirements in the current national
regulations before commissioning in order to maintain the
explosion protection.
• Check the device for proper installation and function before
commissioning.
WARNING
Unauthorized work being performed on the device!
Risk of injuries and material damage!
• Work performed on the device must only be carried out by
appropriately authorized and trained personnel.