SPX Cooling Technologies Marley Sigma Marley Sigma Steel Engineering Data Download Page 5

Marley 

/

 

Sigma Steel 

Cooling Tower 

/

 

 

5

only accomplish the specified thermal performance—

but which will include normal operation- and mainte-

nance-enhancing accessories and features. It will also 

incorporate those standard materials which testing 

and experience has proven to provide best results in 

normal operating conditions.

Pages 20 thru 27 provide some paragraphs intended 

to add those features, components, and materials that 

will customize the tower to meet the user's require-

ments.

 

Space does not permit definition and explanation of 

all of the possible options that can be applied to the 

Sigma Steel. SPX Cooling Technologies realizes that 

you, the purchaser, must be happy with the tower's 

characteristics, and we are prepared to provide—or 

provide for—any reasonable enhancement that you 

are willing to define and purchase.

Your needs will become part of the continuing better-

ment of this Marley product line.

T

he Sigma Steel

 is a galvanized steel, field-erected, 

general purpose crossflow cooling tower, designed 

to serve normal air conditioning and refrigeration sys-

tems as well as medium sized industrial loads. Evolv-

ing from the crossflow concept of towers pioneered 

by Marley in 1938, and incorporating over 70 years of 

design advancements, the Sigma Steel represents the 

current state of the art in this cooling tower category.

 

This booklet not only relates the language to use in 

describing an appropriate Sigma Steel cooling tow-

er—but also defines why certain items and features 

are important enough to specify with the intention of 

insisting upon compliance by all bidders. The left-hand 

column of pages 11 thru 25 provides appropriate text 

for the various specification paragraphs, whereas the 

right-hand column comments on the meaning of the 

subject matter and explains its value.

Pages 12 thru 19 indicate those paragraphs which will 

result in the purchase of a cooling tower which will not 

Summary of Contents for Marley Sigma Marley Sigma Steel

Page 1: ...Marley Sigma Steel CoolingTower Engineering Data Specifications...

Page 2: ......

Page 3: ...m 18 Casing 18 Access 18 Cold Water Collection Basin 19 Scope of Work 19 Specifications Options Control Options Control System 20 Basin Heater 21 Fan Motor Variable Speed Drive 21 Marley Premium VFD S...

Page 4: ......

Page 5: ...rt of the continuing better ment of this Marley product line The Sigma Steel is a galvanized steel field erected general purpose crossflow cooling tower designed to serve normal air conditioning and r...

Page 6: ...model indicates number of cells Change as appropriate for your selection Primary engineering data is per cell 3 Height shown is from base of tower columns to top of fan cylinder 4 Pumping head shown i...

Page 7: ...ain at least 2 0 of clear space at tower endwalls for construction purposes Air inlet faces must have unobstructed air supply If obstructions exist nearby consult your Marley sales representative 4 Op...

Page 8: ...r Marley sales representative 4 Minimum basin depth is 1 6 Basin depth may vary to suit your storage requirements 5 All anchor bolts complete with nut and washer must be furnished by others Bolts must...

Page 9: ...required 4 Marley piping terminates at face of a cast iron flat face flange Bolt circle conforms to class 125 lb ANSI B 16 1 specifications 5 Supports on tower for crossover piping are part of the tow...

Page 10: ...esigner must take care to provide generous air inlet paths and the tower s fan cylinder discharge height should not be lower than the elevation of the top of the enclosure Obtain a copy of Marley Tech...

Page 11: ...u money in the long run both on operation and on maintenance Here are two of the more popular options Two Speed Motors Two speed motors improve operating flexibility by increas ing the number of poten...

Page 12: ...ection that fits your space allot ment and whose power usage is acceptable Limitations on physical size and total operating horsepower avoid the introduction of unfore seen operational and site relate...

Page 13: ...ase is incapable of performing as specified then you will not have received full value for your money Bear in mind that the size and cost of a cooling tower varies directly with its true thermal capab...

Page 14: ...wind load and 5 g seismic load Framing joints shall be made with 1 2 diameter and larger Series 300 stainless steel machine bolts nuts and washers 3 4 Towers of more than one cell shall include galvan...

Page 15: ...surance that the tower can withstand long term operation in a hostile environment but that it will accept many years of inspection and maintenance traffic by your operating personnel Fiberglass reinfo...

Page 16: ...s a crossover pipe to deliver water to both sides of the tower 5 6 The mechanical equipment assembly shall be warranted for no less than five 5 years This warranty shall cover the fan s speed reducers...

Page 17: ...parate external louvers used by others permit water to escape the fill and form ice or produce an unsightly situation adjacent to the tower If you plan to use your tower in the wintertime particu larl...

Page 18: ...d steel shall also be provided 9 0 Access 9 1 There shall be a 33 wide by 61 high access door in each endwall casing to provide access to the interior of the tower Access doors shall be hinged and equ...

Page 19: ...be responsible for the design fabrica tion and delivery of materials to the project site and for the erection of the tower over supports provided by others Unless otherwise specified all external pipi...

Page 20: ...20VAC 50VA control power overload trip alarms and remote temperature control devices The temperature controller shall be adjustable for the required cold water temperature If a thermostatic controller...

Page 21: ...drive shafts The VFD shall catch a fan spinning in the reverse direction without tripping The panel shall include a main discon nect with short circuit protection and external operating handle lockabl...

Page 22: ...is no longer required The fluid cooler manu facturer shall supply VFD start up assis tance Tower vibration testing throughout the speed range is required to identify and lockout any natural frequency...

Page 23: ...assure proper gear box lubrication the VFD sys tem shall de energize the motor once 25 motor speed is reached and cool ing is no longer required The VFD shall include de icing logic with auto canceli...

Page 24: ...the ladder attached to the tower casing This extension shall be long enough to rise from the roof grade level to the base of the tower Anchorage and lateral bracing of the ladder extension shall be by...

Page 25: ...r Distribution System Section The distribution basins shall include galvanized steel covers These covers shall be designed for a uniform live load of 40 psf and shall be easily removable for maintenan...

Page 26: ...usually resolve these situations by using two speed motors in either 1800 900 or 1800 1200 RPM configuration and operating the fans at reduced speed without cycling after hours The natural nighttime r...

Page 27: ...n in the tower Refer to our Stainless Steel Sigma Series in which the use of stainless steel has been maximized Except for valve bodies and Geareducer every steel component of that product line is man...

Page 28: ...66213 UNITED STATES 913 664 7400 spxcooling spx com spxcooling com In the interest of technological progress all products are subject to design and or material change without notice 2008 SPX Cooling T...