GETTING STARTED

BEFORE YOU BEGIN

• 

Read, understand and follow these instructions.

• 

Barricade the work area.

• 

Review and prepare to complete the installation checklist as the installation progresses.

If you have questions on other wetwell installation details, call Technical Support at +61 2 8705 0255

Site 
Preparation 
 

It is best practice to prepare the excavation for the Vortceptor separation 
chamber first. The Vortceptor separation chamber is the blue fibreglass 
vertical tank, which we will refer to as ‘the Vortceptor’. The excavation for 
the Diversion Chamber (the rectangular precast concrete chamber) follows 
afterwards.  

YES / NO

Prior to installation, the inlet pipe run would typically be installed, within one 
or two pipe lengths prior to the diversion chamber.

YES / NO

Vortceptor 
Installation 

Always physically check measurements on the Vortceptor prior to installation. 

YES / NO

The Vortceptor excavation should be no greater than required, this would 
be 1000mm oversized or to suit shield sizing. This is with due regard to the 
amount of backfill to be used under and around the tank. 

YES / NO

Install a 150mm thick, compacted base. This can be either a concrete blinding 
or compacted crushed rock layer. 

YES / NO

Lower the Vortceptor into the excavation, ensure no rocks or sharp objects fall 
into the hole and damage the tank. 

YES / NO

Level and adjust the Vortceptor to suit the main drain pipework and the 
Diversion Chamber inlet void. The invert levels of the inlet and outlet 
pipework is to match the invert of the inlet and outlet chute of the Vortceptor. 
(The inlet and outlet chute is the rectangular flanged opening on the side of 
the Vortceptor)

YES / NO

Fill the tank with water up to the invert of the inlet - the volume will depend on 
the specific Vortceptor.

YES / NO

Encase & backfill the outside of Vortceptor with an engineer specified material 
– such as graded gravel aggregate, or crushed recycled concrete, or cement 
stabilised sand. 

YES / NO

In installations when the tank is located in an area subject to high water 
table or trapped ground water, the tank must be completely encased in 
unreinforced concrete, up to the specified height above the Vortceptor base, 
and at the minimum specified width beyond the perimeter of the Vortceptor 
base.  Refer to SPEL Stormwater for recommended concrete dimensions and 
volumes to withstand buoyancy forces. 

YES / NO

INSTALLATION CHECKLIST

Summary of Contents for Vortceptor

Page 1: ...SPEL Vortceptor spel com au Installation Manual ...

Page 2: ...y of all the individuals involved in the installation To prevent wetwell damage and or failure which could lead to product loss and environmental contamination To validate the wetwell warranty GENERAL INFORMATION WARNING Wetwells are a confined space per OHS guidelines Follow proper confined space safety procedures SPEL fibreglass wetwells are designed for installation with concrete top pad and bo...

Page 3: ...tank YES NO Install a 150mm thick compacted base This can be either a concrete blinding or compacted crushed rock layer YES NO Lower the Vortceptor into the excavation ensure no rocks or sharp objects fall into the hole and damage the tank YES NO Level and adjust the Vortceptor to suit the main drain pipework and the Diversion Chamber inlet void The invert levels of the inlet and outlet pipework i...

Page 4: ...DS bit to drill the bolt holes YES NO Use M8 x 100mm Galvanised screw bolts to fix the Vortceptor to the Diversion Chamber YES NO Associated Drainage Finishing Works Install upstream and downstream drainage pipework YES NO Connect the pipework by others to the Diversion Chamber concrete bandage the inlet and outlet pipes to the Diversion Chamber YES NO Internally render the inlet and outlet pipewo...

Page 5: ...ntal contamination A HANDLING PREPARATION WARNING Do not stand on or under wetwell while it is being lifted This could result in personal injury or death Do not drop or impact the wetwell Wetwells should be stored horizontally and chocked using only appropriate materials such as sandbags tires or other soft or pliable materials Upon wetwell delivery and when lifting wetwell visually inspect entire...

Page 6: ...are significant and are based on the method of construction not the measured densities Dumped means that there is absolutely no compaction of the embedment soil Slight means there was something done that increased the soil density even if minor such as water settling jet ting flooding equipment travel and in some cases foot traffic For stable soils cohesion 36 kpa and or a bearing capacity 170 kpa...

Page 7: ...as an underground fibreglass tank the backfill around the wetwell must also meet the tank backfill requirements so as to not compromise the tank installation Tank backfill requirements are more restricted and strict conformance to the tank backfill requirments in MAN 600 must be met for both the wetwell and tank F PIPING PENETRATIONS FITTINGS CAUTION Always wear safety glasses and protective cloth...

Page 8: ...ned to be self supporting after cured The pad shall be specified by the Certified Engineer FIBREGLASS FLAT TOPS WITHOUT TRAFFIC LOAD See Figure H 1 The pad must be larger than the wetwell a minimum of 300mm in all directions Maximum 200mm concrete pad thickness FIBREGLASS FLAT TOPS WITH TRAFFIC LOAD See Figure H 2 The pad must be larger than the wetwell a minimum of 600mm in all directions The Cer...

Page 9: ...spel com au 9 ...

Page 10: ...10 Installation Manual Vortceptor ...

Page 11: ...in minimum water level Add a minimum of 300mm of well placed backfill material MUST be crushed gravel to the hole and level the bed to assure uniform bottom support for the tank Position the tank in the hole Partially ballast tank using water until it settles firmly on the prepared bed Ballast level in a tank must never exceed water level in hole during installation Use only enough ballast to sink...

Page 12: ...ab Thickness mm Required Ballast Extension Around Wetwell mm Ballast Height mm 1200 1 1800mm Dia N12 400 200 300 400 1520 1 1920mm Dia N12 500 200 350 500 1850 1 2250mm Dia N12 1 2650mm Dia N12 550 200 400 600 2200 1 2600mm Dia N12 1 3000mm Dia FN12 700 200 500 700 2470 1 2900mm Dia N16 1 3300mm Dia N16 800 250 500 800 3000 1 3400mm Dia N16 1 3800mm Dia N16 900 300 700 1000 3500 1 3900mm Dia N20 1...

Page 13: ...spel com au 13 ...

Page 14: ...A OFFICE 9 Hampden Road Mount Barker SA 5251 P 1300 773 500 E sales spel com au WA OFFICE 2 Modal Crescent Canning Vale WA 6155 P 61 8 9350 1000 P 1800 335 550 E sales spel com au NZ OFFICE AUCKLAND 100 Montgomerie Road Airport Oaks P 64 9 276 9045 E sales spel com au NZ OFFICE WANGANUI 43 Heads Road Wanganu New Zealand P 64 6 349 0088 E sales spel com au NZ OFFICE WELLINGTON 41 Raiha St Porirua W...