Spectron Gas Control Systems GmbH
Decommissioning and recommissioning | 9
G56-SP_0520
23
9 Decommissioning and recommissioning
9.1 Decommissioning
The gas supply via the pressure control panel can be interrupted without additional risks. If the
pressure control panel remains unused or disassembled for an extended period, a decommis-
sioning process must be carried out.
In principle, decommissioning must be carried out in In principle, decommissioning must be car-
ried out in the following order:
1. Interrupt gas supply (see "Gas supply interruption").
2. Disconnect the process gas source from the pressure control panel.
3. Seal all open screw connections tightly (e.g. plug on process gas port).
4. Flushing through to the process (see "Flushing through to the process").
5. Close all valves.
6. Switch off controller.
9.2 Recommissioning
The recommissioning of the pressure control panel must be carried out in accordance with the
stipulations in the "
" chapter.