STEP 1: 

Check the following jobsite conditions before starting your project.

 

H = Height

 from roof surface to paver surface 

        Note: This is the desired finished height. 

 

T = Thickness of Paver 

 

S =

 Need for 

Slope Correction

 

        (0-10% slope) 

 

X = Calculated Pedestal Height 

Note: Conditions often vary within the same project zone, so 
Step 1 should be carried out thoroughly.

 

 

STEP 2: 

Use measurements from Step 1 to select your pedestal size: (H - T = X).

 

If 

not using slope correction

, use H 

– T = X to identify 

Pedestal Height 

required. Then turn to 

Appendix B

 and use the 

Pedestal Sizing Chart to select your pedestal for this location on the roof. 

   

Example: Lloyd has H of 5” and T of 2.25”. Using H – T = X, Lloyd calculates 5” –  2.25” = 2.75”. So the correct 

                   pedestal selection is CF2. 

 

If 

using slope correction

, please contact a sales rep for assistance in calculating your 

Pedestal Height.

 

STEP 3: 

Become Familiar With The Basic Pedestal Components.

 

 

 

Component 

Function 

Shim 

Reduces or eliminates rocking of paver and reduces vibration/shifting 
of paver. Available in 1mm or 2mm. Optional add-on. 

Top Slope Corrector 

Compensates for roof slope (up to 5% or more). Optional add-on. This 
component adds approx 1/4” of height to the pedestal (varies with % 
slope). 

Pedestal Top 

Provides the adjustable vertical rise. 

Locking Ring 

Minimizes movement after final pedestal adjustment. 

X-245E Extender 

Added to CF4 or CF5 to achieve pedestal heights over 11”. Optional 
add-on. 

Pedestal Base 

Provides stability. 

Base Extender 

Added to any 

CF pedestal to add 3/8” height. Optional add-on. 

Pedestal Base Pad 

Protects roof membrane and reduces vibration. 

 

 

 

 