Installation Guide
Page
22
of
26
7
Commissioning
7.1
Switching on the sonnenProtect-Plus and the storage system
To switch on the sonnenProtect-Plus and the storage system, proceed as follows:
1-
Ensure, that storage system and sonnenProtect-Plus are disconnected from the
power supply.
2-
Switch on all the dedicated circuits within the sub-board.
3-
Switch on the circuits within the sonnenProtect-Plus including the AC-coupled PV
system (if any) and the sonnen Power Meter.
4-
Switch on the grid supply to the storage system and the sonnenProtect-Plus.
5-
Switch on the sonnenBatterie Hybrid 9.53 as described in the respective installation
instructions.
7.2
Setting up the sonnenProtect-Plus
Conditions:
The storage system is connected to the router of the home network.
Your laptop or PC also accesses the home network.
Navigate to the following internet address:
https://find-my.sonnen-batterie.com
start the
Commissioning Assistant 2.0
.
Run through the Commissioning Assistant 2.0 and activate the sonnenProtect-Plus as
demonstrated in Figure 15.
Select the
Protect version
as “2500”.
Enter the
Serial number
of the sonnenProtect-Plus. This can be found on the name
plate label provided at the scope of delivery.
Set the
Min. state of charge
. This is a percentage value of the total capacity of the
storage system to be reserved as backup buffer for the sonnenProtect-Plus in the
event of a grid outage. The backup buffer can be changed later as described in the
following section.